PMP Masterclass Module 16 - More Critical Path Calculations

About PMP Masterclass Module 16 - More Critical Path Calculations

Module Content

Video lesson

Critical Path Analysis is a procedure that calculates the critical path and floats in a network, and analyses this information to predict project duration.

Video lesson

Here we examine the Gantt Chart and schedule baseline, and how it shows early and late task dates. You will learn an overview of resource management and how it applies to the project schedule.

Video lesson

Unlimited resources, moving activities within their free and total slack, to achieve a ‘smooth’ and manageable resource profile across the project WITHOUT moving the project end date. Resource Levelling. Using fixed or limited available resources, moving activities within their free and total slack if that is possible, to achieve an achievable resource profile and with a realistic project end date.