PRINCE2 7 End Stage Assessment 

 May 3, 2023

By  Dave Litten

Authorize a stage or exception plan

It is important that a stage starts only when the project board says it should.

To make that informed decision, the project board needs to review the performance of the current stage (the stage that is just finishing) and improve the stage plan for the next stage.

Prince2 7 End Stage Assessment Prince2 End Stage Assessment
PRINCE2 7 End Stage Assessment 1


The project board authorizes a stage by reviewing the performance of the current stage and approving the stage plan for the next stage. Approval of stage plans occurs prior to every stage.

The project board delegate project assurance by instructing a person or group to undertake some
of the reviewing and assessing actions, such as inspecting the stage plan to confirm it is viable.
Where project assurance activities are delegated, the project board remains accountable.

Recommended actions for the project board:

  • review and approve the end stage report.
  • review the stage plan or exception plan for which the project manager is seeking approval.
  • make a decision to approve the plan or ask the project manager to revise the rejected plan or instruct the project manager to initiate premature closure of the project.
  • communicate the status of the project to the business and keep other interested parties informed about project progress (in accordance with the communication management approach).

To do this effectively, the information presented must be at both stage and project levels, including reviewing the PRINCE2 business case.

Prince2 7 End Stage Assessment Prince2 End Stage Assessment
PRINCE2 7 End Stage Assessment 2

PRINCE2 end-stage assessment

To help prepare for a PRINCE2 end-stage assessment, the project board may involve project assurance to conduct some of the reviewing and assessment.

As part of this review and assessment, the following PRINCE2 products will need to be created, updated, or distributed:

  • Specialist products
  • End stage report
  • Lessons report
  • Follow-on action recommendations
  • Stage plan for the next stage
  • Updated project initiation documentation
  • Updated benefits review plan

All of the above will need to be ultimately approved by the project board executive. In the case of the updated benefits review plan, corporate/programme management will also need to approve it.

PRINCE2 end-stage assessment

The primary purpose is to ensure that the project board (including customers and users) agree that the products produced are acceptable and that the next stage plan is realistic and achievable.

In most cases, the end-stage assessment will be a meeting, allowing a free exchange of opinions, concerns and perceptions. In addition, it is an effective way to gain agreement to proceed or otherwise from the main project stakeholders.

The meeting should not be used to give out new information but merely to decide what to do next. For this reason, essential documentation should be circulated before the end-stage assessment so that all concerned understand the current stage and project status.

With this in mind, it makes sense to send out all such information before the meeting so that it can be reviewed in detail before the meeting.

An end-stage assessment agenda should be created, reviewed, and agreed upon by the project board executive.

The agenda should include all those who need to attend.

The two key documents here are the end-stage report and the next-stage plan. The project manager should highlight any aspects that require human or otherwise resources from internal or external suppliers.

Prince2 7 End Stage Assessment Prince2 End Stage Assessment
PRINCE2 7 End Stage Assessment 3

The end-stage assessment should be based on presenting critical data within the end-stage report.

Prince2 7 End Stage Assessment Prince2 End Stage Assessment
PRINCE2 7 End Stage Assessment 4

Typical information that will need to be presented and explained should include:

  • Milestone reporting
  • Planned and actual delivery dates
  • Reporting of project finances
  • key risks derived from the risk log
  • Quality statistics
  • Investment appraisal

Part of the presentation will include progress information, which should be no surprise to the project board since they have received regular highlight reports. Still, progress should be summarized at the stage and project level.

The appropriate representation must be made at the end stage of assessment by those providing resources for the next stage, as part of the decision-making process will include their agreement that such resources are available.

The project manager will most likely present the above points and should be prepared to explain any deviations from the approved plans. In addition, the project manager should highlight any severe risks relevant to the next stage and gain acceptance of the risk response actions.

Concerning quality statistics, the project manager should be prepared to explain any products requiring rework after the quality reviews.

All products accepted in the current stage may be stored safely or deployed into the life business area.

Such products should have been verified that the above storage or Handover has been carried out per the change management approach document, and if deployed, ensure that operational and maintenance arrangements exist for each product.

The investment appraisal extracted from the updated business case should also be summarized here and, in particular, highlight any metrics that I have changed since the last end-stage assessment, including explaining if required.

Since the next stage plan will have been given out before the meeting, it is to be expected that some questions or comments will be made, and the project manager should be prepared to provide a satisfactory answer or to agree that the next stage plan will be amended to include the information regarding their comments.

The next stage plan will include new or modified product descriptions, which will also need to be agreed upon, particularly the quality responsibilities and criteria.

Some other documents within the project initiation documentation will need to be updated based on current and forecast progress. In addition, from lessons learned, any strategies, processes, or techniques may also need to be modified in the light of experience.

The end stage assessment must include a decision as to whether the project is to proceed to the next stage, some form of corrective action taken and the meeting re-booked for a later date, or whether the project is to be stopped.

The project’s status should be communicated to corporate or programme management and other interested parties in the communication management approach document.

This course is DEPRECATED

The old PRINCE2 6th Edition Foundation and Practitioner syllabus was upgraded in 2024. Check out the brand NEW PRINCE2 7th Edition Masterclass, covering all the current syllabus, training material and online exam benefits HERE

5.0
Prince2 Practitioner Masterclass

Your Route To PRINCE2 6th Edition Practitioner

Study PRINCE2 6 Foundation and Practitioner Exams with our famous on-line course with streaming HD Video Lessons, study guides and mock exams. In the last fifteen years we have had 6,000+ Academy students successfully transform their careers as PRINCE2 Practitioners.

  • Bite Sized Lessons  The sheer size of PRINCE2 can be daunting. The Masterclass will guide you through the syllabus in easy to consume bite sized lessons
  • Be prepared and confident for the exams  Test your knowledge in a fun, entertaining environment with the PRINCE2 Foundation & practitioner exam revision tools
  • Enjoy yourself!  This PRINCE2 Foundation & Practitioner online course is broken into bite-size lessons, combining leading edge multimedia and interactive exercises for optimum enjoyment and knowledge retention
  • Feel confident with full tutorial support  Benefit from fast access to experienced, one-to-one learning support as you study via email and phone, so there is no need to feel isolated while you are learning
  • Take your time  Study at your own pace by bookmarking your progress and picking up where you left off at a speed that suits you

Dave Litten


Dave spent 25+ years as a senior project manager for UK and USA multinationals and has deep experience in project management. He now develops a wide range of Project Management Masterclasses, under the Projex Academy brand name. In addition, David runs project management training seminars across the world, and is a prolific writer on the many topics of project management.

Your Signature

{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}
Insert Content Template or Symbol

Join NOW!

Boost Your Career Now!

15% Discount on all courses with Coupon Code - PROJEX15