What is PRINCE2 controlling a stage process? 

 February 27, 2016

By  Dave Litten

PRINCE2 controlling a stage

The controlling a stage process is used to assign the work within a work package to the specialist team.

The specialist team will execute the work package and create the products.  Controlling a stage is used by the project manager to monitor this work, manage any issues that arise, deal with risks, report on the progress of the stage to the project board via the regular highlight report, and take corrective actions whenever needed to ensure that the stage completes within tolerance.

The main focus of controlling a stage is on delivery of the stage’s products, which were agreed at the start of the stage.  Any potential variations on this are carefully monitored to ensure that the original scope of the stage is maintained.

Another important aspect is that the Business Case should be kept under review throughout the stage and any situations that may impact the Business Case is should be dealt with by the project manager if appropriate, or escalated to the project board.

The project manager must keep a focus on the six performance parameters within PRINCE2: time, cost, quality, benefits, risk, and scope.

PRINCE2 Controlling a Stage – summary

The controlling a stage process describes the work of the project manager in handling the day-to-day management of the stage.  At the end of each delivery stage, the project manager will use the managing a stage boundary process to prepare for the end stage assessments, however, in the final stage, the project manager will use the closing a project process to ensure the project is shut down in a controlled manner.

Optionally, the controlling a stage process may be used during the initiation stage, particularly if this stage is lengthy or risky.

The day to day management of the stage consists of authorising the work to be done, monitoring progress against that work and ensuring that product quality is being met.

It also includes giving regular highlight reports to the project board on the progress of the stage, assessing and dealing with issues and risks, and taking corrective action if required.

The activities used in the Controlling a Stage process are:

  • Authorize a Work Package
  • Review Work Package date has
  • Receive completed Work Packages
  • Review the state status
  • Report highlights
  • Capture and examine issues and risks
  • Escalate issues and risks
  • Take corrective action

This course is DEPRECATED

The old PRINCE2 6th Edition Foundation and Practitioner syllabus was upgraded in 2024. Check out the brand NEW PRINCE2 7th Edition Masterclass, covering all the current syllabus, training material and online exam benefits HERE

5.0
Prince2 Practitioner Masterclass

Your Route To PRINCE2 6th Edition Practitioner

Study PRINCE2 6 Foundation and Practitioner Exams with our famous on-line course with streaming HD Video Lessons, study guides and mock exams. In the last fifteen years we have had 6,000+ Academy students successfully transform their careers as PRINCE2 Practitioners.

  • Bite Sized Lessons  The sheer size of PRINCE2 can be daunting. The Masterclass will guide you through the syllabus in easy to consume bite sized lessons
  • Be prepared and confident for the exams  Test your knowledge in a fun, entertaining environment with the PRINCE2 Foundation & practitioner exam revision tools
  • Enjoy yourself!  This PRINCE2 Foundation & Practitioner online course is broken into bite-size lessons, combining leading edge multimedia and interactive exercises for optimum enjoyment and knowledge retention
  • Feel confident with full tutorial support  Benefit from fast access to experienced, one-to-one learning support as you study via email and phone, so there is no need to feel isolated while you are learning
  • Take your time  Study at your own pace by bookmarking your progress and picking up where you left off at a speed that suits you

Dave Litten


Dave spent 25+ years as a senior project manager for UK and USA multinationals and has deep experience in project management. He now develops a wide range of Project Management Masterclasses, under the Projex Academy brand name. In addition, David runs project management training seminars across the world, and is a prolific writer on the many topics of project management.

Your Signature

{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}
Insert Content Template or Symbol

Join NOW!

Boost Your Career Now!

15% Discount on all courses with Coupon Code - PROJEX15