Quality Management Strategy in PRINCE2
The problem with the word quality is that it is used everywhere and ceases to have any real value. This is a danger when it comes to projects, as the last thing we want is when at the end of the project we seek acceptance from the customer, and an argument commences about what quality really is and what their expectations were. It’s far better to have a quality management strategy so that all stakeholders know what quality means and how it is to be applied to this particular PRINCE2 project.
It is far better to have these discussions at the very beginning of the PRINCE2 project, so that expectations can be agreed and customer quality satisfaction assured.
Put simply, a key success factor of any PRINCE2 project is that it delivers what the user expects and finds acceptable. The purpose of the Quality Management Strategy is to ensure such agreements are captured and maintained throughout the project.
PRINCE2 develops a set of key management products that ensures that the project is on a consistent pathway to quality and quality management strategy.
As part of the PRINCE2 Project Brief, the Project Product Description was created in the Starting Up a Project process. It is now reviewed again to check that the customer’s quality expectations and acceptance criteria are sufficiently defined.
Of equal importance is that any corporate or programme management strategies, standards or practices relating to quality management replied by this project, and these must be built into the PRINCE2 quality management strategy document.
Don’t forget to ensure that both the customer and supply-side are involved in determining what these are in the quality management strategy, and how they should be applied to this project.
Any lessons from previous similar projects should be captured and used to help define the Quality Management Strategy. In a similar way, the risk and issue registers should be checked for any risks and issues associated with quality management.
PRINCE2 Quality Management Strategy information:
- Any special quality management procedure to be followed
- Any records that will be checked including tools and techniques to be used
- How reporting on the quality management procedure performance will occur
- The roles and responsibilities for quality management activities, including linkages if required, to corporate or programme quality assurance functions.
- The Quality Management Strategy needs to be reviewed by Project Assurance.
The Quality Register for this project must now be created as this too will be included within the quality management strategy. Once the second Stage Plan has been created, this register can be populated with the planned dates for quality management activities of the stage. During the second stage, as quality management activities take place, the actual dates can be added as laid down in the quality management strategy.
In this way the quality register is used as a management tool to ensure that the prerequisite quality of the projects products and that the management of the project is being undertaken in a quality manner.
Any new risks or issues related to quality management should be captured and appropriate responses and actions taken. The project board may review the Quality Management Strategy document at this point or when reviewing and approving the Project Initiation Documentation.
This course is DEPRECATED
The old PRINCE2 6th Edition Foundation and Practitioner syllabus was upgraded in 2024. Check out the brand NEW PRINCE2 7th Edition Masterclass, covering all the current syllabus, training material and online exam benefits HERE

Your Route To PRINCE2 6th Edition Practitioner
Study PRINCE2 6 Foundation and Practitioner Exams with our famous on-line course with streaming HD Video Lessons, study guides and mock exams. In the last fifteen years we have had 6,000+ Academy students successfully transform their careers as PRINCE2 Practitioners.