PRINCE2 Primer Process Road Map 

 January 4, 2017

By  Dave Litten

PRINCE2 Primer Process Road Map – A special InfoGraphic

After the graphic below showing how the PRINCE2 Processes interact, I have given a detailed description which can be read in conjunction with the graphic itself.

The PRINCE2 Primer Process Road Map is a large graphic (You can download the original large file HERE.)

Dave Litten

PRINCE2 Process Road Map

Prince2 Roadmap 2020
PRINCE2 roadmap 2020

I will start at the top left-hand corner of the diagram with the ‘trigger’ for any PRINCE2 project – the Project Mandate.

A project can be standalone or part of a programme, in which case a project may be triggered from either those within a programme, here called programme management, or by appropriate senior management within an organization, here called corporate management.

A PRINCE2 project is therefore triggered by either of the above by issuing a Project Mandate. This document should contain as a minimum, the name of the prospective project board executive and the reasons for the need of the project. As such it may only be a verbal instruction or possibly an e-mail. At the other extreme it could be the final report from a feasibility study. Whichever, it must contain sufficient information provided by an appropriate authority level, in order to trigger the first PRINCE2 process.

The first process is called Starting Up a Project and uses the initials SU. This occurs pre-project, and is used as a solid foundation prior to the first stage in a PRINCE2 project.

One of the first activities is to appoint the Executive of the Project Board and the Project Manager; the Executive will now design and appoint the remaining roles within the PRINCE2 Project Board including who will fill the Senior User and Senior Supplier roles, and how Project Assurance is to be handled. The project manager will design and appoint any other supporting roles that will be needed such as project support, configuration management and the optional Team Manager role.

There are two main management products that are an output from this process, the Project Brief and a plan for the Initiation Stage.

The Project Brief contains the outline Business Case with sufficient information to justify carrying out the initiation stage, creating the Project Product Description which includes aspects such as the customer’s quality expectations and acceptance criteria for the end product of the project.

The Project Brief also contains the Project Approach management document. This lays out the approach used by the project to deliver the end product, for example, basing the design on an existing product or developing an entirely new design, or whether or not resources used for the project will be provided internally or by the use of third parties.
One important principle of PRINCE2 is that of management by exception. The purpose of this is to set tolerance levels at the directing, managing, and delivering management levels within a project. Tolerance is defined as limit within which a particular level may manage without the need to escalate to the next level above.

Corporate or Programme management have the authority to set project level tolerances, the Project Board have authority to set stage level tolerances, and optionally, the Project Manager may set tolerances around a particular Work Package.

The Lessons Log is created and filled with any lessons that can be learned from appropriate individuals and previous similar projects. The Lessons Log will be updated and used throughout the project, in particular as a source of information to create the optional Lessons Report at the end of each stage, and the Lessons Report that is created as part of the Closing a Project process.

In this way, lessons can be passed on to future similar projects.

The Daily Log is also created by the project manager, and is used as a ‘diary’ by the project manager for the remainder of the project. But here in SU, it is also used to capture any risks and issues that need to be managed prior to the formal start of the project.

To proceed any further, the newly formed project board will need to make a decision whether or not it is worth investing in the creation of the PID. In particular how much work effort and resources are needed in the initiation stage. The information contained within the Project Brief and the initiation Stage Plan will give the project board sufficient information to make an informed choice.

The Starting Up a Project process culminates with the project manager requesting that the project board consider authorizing the initiation stage. This uses the first activity ‘authorizing initiation’ within the directing a project (DP) process. The project board may decide not to proceed any further.

The initiating a project process is used within the initiation management stage and the main deliverable here is the PID itself. The activities within this process echo the contents of the project initiation documentation.

The Risk Management Strategy document is created and the Risk Register is set up to capture and manage any risks throughout the project. The Risk Management Strategy defines HOW resource will be managed throughout the project.

The Quality Management Strategy document is created and the Quality Register is set up. This register will typically be empty at this point, as this will contain the planned dates of all quality management activities for the creation of the specialist products, and such dates will not be known until the second Stage Plan is created.
This second stage is always the first delivery stage, so-called because this is the first stage (and possibly also the final stage for small simple projects) where specialist products are to be created. The word specialist product refers to the type of project and the specialist skills required.

The Configuration Management Strategy document is created and the Issue Register is set up. In PRINCE2, an issue can be advice of a new risk, a problem or concern, or a change.

Configuration management may be thought of as version control and as such is closely aligned with how change control (mentioned above) is to be implemented. Typically configuration management will be supplied by the project support role.

The final strategy is the Communication Management Strategy, and is created last because the first three strategies will have communication needs and these can be included at this point. As you can see, all four of the strategies are HOW-TO documents.

The Project Plan can now be created in parallel with setting up the various controls there will be needed throughout the project. Typically these controls focus on those needed at project board level for example end stage assessment timing, and the frequency of their regular Highlight Reports, while at project manager level for example, the formality or otherwise of issuing Work Packages and the frequency of the regular Checkpoint Reports.
Highlight Reports cover progress within the management stage, and Checkpoint Reports cover the progress of specialist product creation within a Work Package.

As with all plans, the Project Plan is a document, and will use the PRINCE2 product-based planning technique.
The next step would be to create Product Descriptions for all appropriate lower level products, including their quality criteria. The final product based planning step is to create a Product flow Diagram, which shows the sequence of creation of the products.

In case you are confused, an activity would normally be described with a noun and verb such as ‘create report’, whereas a product would be described with a noun or outcome for example ‘specification document’.

Within PRINCE2, the next steps cover traditional planning techniques, first identifying the activities needed to create each product, then estimating such activities, creating the schedule or sequence of such activities (usually shown as a network diagram or Gantt Chart view). Then going on to identify risks, their associated response activities, and finally adding the narrative of the plan document. The number of PRINCE2 Stages for this project would need to be agreed.

Product Descriptions along with their quality criteria will be created along with a Configuration Item Record (CIR) for each product. This record forms part of the data and the status for each product held within configuration management.

Also at this point the Project Product Description may now needs to be further refined, for example, as better data is understood for the acceptance criteria of the project end product.

The detailed Business Case can now be developed as it will use timescale and cost information derived from the Project Plan. This detailed Business Case will be used throughout the project in particular at the end of each management stage where it is updated and used as a basis to proceed or otherwise by the project board.

A new management product is now created based upon some information contained within the business case, and it is called the Benefits Review Plan. As the name suggests, this contains a description of each future benefit, its timing, measurement, and the resources required to carry this out.

All of the above can now be assembled and forms the Project Initiation Documentation (PID). The project manager will now request that the project board authorize the project.

Authorizing the PID will occur within the Authorize the Project activity and authorizing the next Stage Plan will occur at the Authorize a Stage or Exception Plan activity. Both of these are activities within the Directing a Project process, and will normally take place at the same meeting which is the end stage assessment.

At this end stage assessment, as is typical, the project board has the option to approve the next Stage Plan or prematurely close the project.

Assuming all is well, the Project Board will set stage tolerance for the next stage, advise the project manager of the frequency and detail to be included in the regular Highlight Reports and approve the next Stage Plan. This will now trigger the project manager to give out the first Work Package within this newly approved stage.
The PRINCE2 method defines that the specialist team should not start work on any product creation until a Work Package containing such work has been authorized by the project manager and accepted by either the team manager or the team members themselves.

Every Work Package must contain at least one Product Description. The project manager may optionally set tolerances at the work package level.

Once the Work Package has been agreed and accepted then work can start on the creation of the specialist products contained within the Work Package.

The ‘execute a work package’ activity is where the specialist products are created and their quality checks carried out, followed by their approval by the appropriate authority or individual.

The team manager or the team themselves will produce regular Checkpoint Reports providing information on the status and future forecast of the creation of specialist products. These are sent to the project manager, and may be in the form of a report or a meeting.

The project manager will use the activity of Review Work Package Status to determine the progress or otherwise of the creation and the approval of these specialist products.

Since the Stage Plan has been approved by the Project Board, then the project manager must look at progress within the stage itself. If the project manager determines that the stage is forecast to remain within tolerance bounds, then he or she may take some form of corrective action to minimize any such deviations within tolerance. This may entail giving out new or modified Work Packages to the specialist team.

In addition to this the project manager will need to review the stage status and use the activity of report highlights, which will generate a Highlight Report to be given to the project board so that they understand the current status and forecast future of progress within the stage. The project manager will update the Stage Plan with actual progress, and modifying future actions to ensure that the stage plan is forecast to complete within tolerance.

As each Work Package is completed, then the team manager or the specialist team themselves needs to inform the project manager that the Work Package is indeed complete. The project manager, as part of the activity review work package status will need to agree that all the products have been completed, met their quality criteria, and have been approved by the appropriate authority.

This may trigger the authorization of a new/revised Work Package, or that the stage end is approaching, in which case the project manager would use the Managing a Stage Boundary (SB) process to prepare for an end stage assessment.

If at any time during the stage, either issues or risks should arise, then the project manager should use the activity of capture and examine issues and risks to carry out an impact analysis of these on both the stage and project. The appropriate Issue Register or Risk Register should be updated with such information.

If the project manager determines that some corrective action can be taken via the issue of new or modified Work Packages to resolve the situation then such actions would need to be taken.

If after impact analysis and the review this showed that forecast of tolerances would be exceeded, then the project manager must create an Exception Report and bring this to the attention of the project board.

The Exception Report should contain information on the reasons for this forecast of exceeding tolerances, the impact in terms of the appropriate tolerance, and a set of options, which if implemented would return the stage of project within tolerance bounds, and a recommendation of which option should be chosen, and why it is the best option.

This is sent to the project board who now need to make a decision on what to do next. One option they have is to prematurely close the project, in which case the project manager would use the Closing a Project (CP) process to carry this out. We shall assume that they prefer another option, either recommended by the project manager, or one which they have determined. This would trigger the project manager to use the Managing a Stage Boundary (SB) process.

The project board would request the preparation of an Exception Plan using the Managing a Stage Boundary process.

At this point it would be helpful to state that the Managing a Stage Boundary process has only TWO uses. The first is to prepare for an end stage assessment (ESA) by creating the next Stage Plan.

The second is to prepare for an exception assessment (EXA). In the former the objective is to approve or otherwise, the next Stage Plan, and in the latter it is to approve or otherwise the Exception Plan.

So the steps would be:

  • Create either a next Stage Plan or an Exception Plan
  • Update the Project Plan to show actual progress and forecast
  • Some aspects of the PID may also need to be updated, possibly in terms of the strategies, the plan, and the controls, or the Business Case and related Benefits Review Plan.

As a result of the above, new or modified Product Descriptions will need to be created, new or modified risks and issues entered on to the appropriate registers including any lessons that have been learned during the stage.
The Benefits Review Plan needs to be updated to reflect any products that may have already being released into the operational (business as usual – BAU) areas.

The project manager will produce an End Stage Report and if appropriate create a Lessons Report.

The project board will need to make a decision to either approve the next Stage Plan, or approve the Exception Plan, or request more information, or to order a premature close of the project.

Once this has been authorized, the project manager will give out the work contained within that Stage Plan and the specialist team will create the specialist products via each Work Package. When the last Work Package has been completed (each specialist product has been approved), then this will trigger the project manager to acknowledge that the project end is approaching if this is the last delivery stage in the project.

If the project needs to be brought to a premature close, then the closing a project process (CP) is used.

A final management stage is not used to merely to use the Closing a Project process as the final stage of a project will use the Controlling a Stage, Managing Product Delivery, and Closing a Project processes.

Assuming a natural close to the project, then the ‘prepare planned closure’ activity will be used. The project manager would request a product status account to ensure that all products within the project would have been approved and that the project acceptance criteria have been met. The Project Plan should be updated with the ‘actuals’ of this final stage.

The project’s products must now be handed over to the operational and maintenance environment, where they will be used to ultimately realise the benefits contained as stated within the Business Case. The project manager would updates relevant configuration item records to show that such products have the status of ‘operational’, any acceptance records should be created or obtained, and the Benefits Review Plan updated to reflect any products that have already realized benefits and to include any post project activities for such benefits that have yet to be realized.
The evaluate the project activity will create the end project report to capture actual progress and aspects such as project performance metrics, and will include the Lessons Report based upon the information contained within the Lessons Log.

In the case of premature close, then the reasons for this should be entered and updated on the Issue Register, and if necessary any additional work may be needed to buy the complete unfinished products or to make them safe. Once the project manager has determined that the project should and can be closed, then a recommendation of such should be raised to the project board in the form of a closure recommendation.

The final activity in any project, is the authorized project closure within the Directing a Project process. The project board would need to review original and updated versions of the PID, review and approve the End Project Report, confirm any follow-on actions or loose ends, verify that the projects products have been handed over in an appropriate manner, ensure that the Business Case remains viable, advise that the project can now be closed, and advise those supplier resources that these can now be withdrawn.

This course is DEPRECATED

The old PRINCE2 6th Edition Foundation and Practitioner syllabus was upgraded in 2024. Check out the brand NEW PRINCE2 7th Edition Masterclass, covering all the current syllabus, training material and online exam benefits HERE

5.0
Prince2 Practitioner Masterclass

Your Route To PRINCE2 6th Edition Practitioner

Study PRINCE2 6 Foundation and Practitioner Exams with our famous on-line course with streaming HD Video Lessons, study guides and mock exams. In the last fifteen years we have had 6,000+ Academy students successfully transform their careers as PRINCE2 Practitioners.

  • Bite Sized Lessons  The sheer size of PRINCE2 can be daunting. The Masterclass will guide you through the syllabus in easy to consume bite sized lessons
  • Be prepared and confident for the exams  Test your knowledge in a fun, entertaining environment with the PRINCE2 Foundation & practitioner exam revision tools
  • Enjoy yourself!  This PRINCE2 Foundation & Practitioner online course is broken into bite-size lessons, combining leading edge multimedia and interactive exercises for optimum enjoyment and knowledge retention
  • Feel confident with full tutorial support  Benefit from fast access to experienced, one-to-one learning support as you study via email and phone, so there is no need to feel isolated while you are learning
  • Take your time  Study at your own pace by bookmarking your progress and picking up where you left off at a speed that suits you

Dave Litten


Dave spent 25+ years as a senior project manager for UK and USA multinationals and has deep experience in project management. He now develops a wide range of Project Management Masterclasses, under the Projex Academy brand name. In addition, David runs project management training seminars across the world, and is a prolific writer on the many topics of project management.

Your Signature

{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}
Insert Content Template or Symbol

Join NOW!

Boost Your Career Now!

15% Discount on all courses with Coupon Code - PROJEX15