PRINCE2 Issue Definition – Part 5 – issues and exceptions 

 July 9, 2023

By  Dave Litten

PRINCE2 Issue Definition – Part 5 – issues and exceptions

Prince2 7Th Edition From Projex Academy

When issues and exceptions need stage correction

If the stage is going off track due to issues and exceptions, then the project manager needs to react with actions that bring it back on track.

The project manager will first learn of such a deviation from the plan when checking the status of the stage. It is important to check concerning issues, where you are to see if you have the capacity to absorb the issue impact of any action, or whether you need to escalate the matter to the Project Board.

The activity you would use there is called “Review the stage status “and it is used to carry out a thorough check on the progress of the whole stage, including any forecasts, to see whether or not you are still likely to finish the stage within its tolerance limits. The stage tolerances were set down by the Project Board at the beginning of the stage.

Just for completeness, do remember there is another activity within the Controlling a Stage process called “Review work package status“. Although this too provides a progress check, it is only done for each work package, and don’t forget you may have several work packages to complete during a stage, and often to or more of them may be executed in parallel. This activity helps in identifying issues and exceptions.

The relationship between issues and risks

I have already given you a simple definition of an issue and a risk, and they are different. But did you know that one can cause the other? If someone raises an issue, as part of carrying out issue analysis you may determine that this particular issue has an impact on one or more risks. The issue could make a risk more likely or less likely, the impact greater or less, or the impact areas may now be different. This is vital when identifying issues and exceptions.

It works that way when managing the risk too. When carrying out risk analysis a new or modified issue may be discovered. Also, as part of resolving a risk, you may only be able to minimize its impact rather than remove it completely. This remaining impact that for now, you can do nothing about, In and of itself could give rise to a new issue.

The PRINCE2 7 Business Case

When managing the details within a stage, it is easy to forget that any issue that is being analysed may have an impact on the Business Case. I’m not just talking about benefits here, but also other aspects of the Business Case such as risks, constraints, timescales and cost. For this reason, tolerances include any benefit tolerances in order to catch any issues and exceptions as the root cause.

Reporting an exception

Any given issue may cause stage or project tolerances to be forecast to be exceeded. As the project manager, if you have determined that no matter what action you take within your authority, you cannot adjust the running of the stage to finish within the limits of the tolerance, you must report this to the Project Board immediately.

The stage is now “in exception “.

The only action you should now be taking is to investigate the size of the problem and the scope of the actions and produce an exception report. The structure of the exception report was laid down within the communications management strategy document.

It is important to realise that the Exception Report is not necessarily a document that may be a meeting, a phone call or an e-mail. Whichever makes the most sense.

It is also worthwhile mentioning common sense. If the forecast deviation of the tolerance is relatively small, then I would recommend immediately contacting the Project Board and discussing this with them verbally. Of course, first, you would want to think through what actions you would take and at that swift meeting get their buy-in to proceed.

Issues and Exceptions

It may be that the actions that you can take to bring the stage back within tolerance may have other impacts such as Business Case impact.

So, whenever an exception occurs, the project manager recommends how it should be dealt with, but it is the Project Board that must decide how it will be dealt with.

About issues, and as part of assembling an Exception report, you would want to check out the Issue Register to determine the latest progress of this or any other issues being currently managed under formal control, and if it has already been created, the formal Issue Report itself.

The PRINCE2 7 Lessons Report

It is worth spending a moment considering the Lessons Report, which after all should be created at the end of each stage and at the end of the project. However, this is the minimum, and frankly, a Lessons Report can be created at any point during the project.

About issues and their inclusion within a Lessons Report, you should consider any statistics such as trends for issues and exceptions. The statistics may be helpful with resourcing similar future projects or future stages.

When detailing issues and exceptions within the Lessons Report, the following areas should be considered:

  • What specific event led to the lesson – Or perhaps it was a constraint
  • Did the issue lead to a good or bad impact? Do not forget that an issue may be a good idea rather than a problem or concern
  • Lay down exactly what triggered the event that led to the issue and the lesson that was learned
  • Were there any early warning indicators or signs that this issue was about to emerge
  • What actions were taken to resolve or minimize the issue and what might be recommended if this occurred again

I mentioned earlier that issues and risks were related, and it is here that you should mention whether the trigger event had been previously identified as a risk – either as a threat or an opportunity.

The Issue Register and follow on action recommendations

I do want to briefly mention that as the project comes to a close, you will be using the Closing a Project process. As part of that, you will want to close down the Issue Register.

Follow-on action recommendations are what the Project Board recommended for the organization to do after the project has finished. It is important to include any recommendations based on issues and exceptions.

But you may carry some entries forward into follow-on action recommendations, an example here is a good idea that you would recommend the organization to do after the end of the project.

PRINCE2® 7 Foundation and Practitioner

5.0
Prince2 Practitioner Masterclass
Prince2 Axelos Peoplecert Trademark Copyright

Learn PRINCE2® 7 Foundation and Practitioner Online

** Enhance your PRINCE2 career now **

PRINCE2® Masterclass gives you the skills necessary to manage projects effectively and achieve your objectives.

  • Optional:   Official Online Exam
  • Course type: E-learning
  • Duration: Approx 45 hours
  • Delivery: Online

Get 7 days a week 12 months one to one coaching with ex PRINCE2 examiner Dave Litten.

PRINCE2® is a globally recognized project management framework. By completing both the Foundation and Practitioner courses through our self-paced e-learning, you will develop an understanding of the methodology and learn how to effectively adapt it to any project.

The PRINCE2® 7 Foundation and Practitioner Masterclass is PeopleCert Accredited and guarantees to take you from PRINCE2 Novice to PRINCE2 Practitioner with our famous video learning, study guides and practice exams.

  • Overview

  • Objectives

  • Exam information

  • Duration

What Does the Masterclass Cover?

The PRINCE2 Foundation examination assesses your knowledge and comprehension of the PRINCE2 project management methodology as detailed in the syllabus. The PRINCE2 Practitioner examination, on the other hand, gauges your ability to apply and tailor the PRINCE2 method. Candidates who pass the Practitioner exam should be able to start implementing the method on an actual project with some guidance. However, their effectiveness may differ based on their experience in project management, the complexity of the project, and the level of support they receive in their work environment.

  • Prepare for your PRINCE2 7 Foundation and PRINCE2 7 Practitioner Exams with our famous on-line course with streaming HD Video Lessons, PDF study guides and Mock Eams. 
  • We are a PEOPLECERT (AXELOS) Business Partner – Our PRINCE2 Masterclass is fully certified for PRINCE2 7th Edition Foundation and Practitioner.
  • Bite Sized Lessons  The sheer size of PRINCE2 can be daunting. The Masterclass will guide you through the syllabus in easy to consume bite sized lessons
  • Enjoy yourself!  This PRINCE2 Foundation & Practitioner online course is broken into bite-size lessons, combining leading edge multimedia and interactive exercises for optimum enjoyment and knowledge retention
  • Take your time  Study at your own pace by bookmarking your progress and picking up where you left off at a speed that suits you
  • Be prepared and confident for the exams  Test your knowledge in a fun, entertaining environment with the PRINCE2 Foundation & practitioner exam revision tools
  • In the last 20+ years we have had 9,000+ Academy students successfully transform their careers as PRINCE2 Practitioners.

Dave Litten


Dave spent 25+ years as a senior project manager for UK and USA multinationals and has deep experience in project management. He now develops a wide range of Project Management Masterclasses, under the Projex Academy brand name. In addition, David runs project management training seminars across the world, and is a prolific writer on the many topics of project management.

Your Signature

{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}
Insert Content Template or Symbol

Join NOW!

Boost Your Career Now!

15% Discount on all courses with Coupon Code - PROJEX15