PRINCE2 Tolerance – the management missing link!
Tolerance and human nature can get in the way of delivering successful projects, and that’s a fact!
Whenever the PRINCE2 term ‘Tolerance’ is mentioned, most humans think, ” Give them an inch – and they’ll take a mile!” So Tolerance is often issued out like a miser giving to charity!
If so, novice PRINCE2 project board members and project managers have yet to grasp the significance of Tolerance; the thinking needs to be entirely different.
Tolerance is a control and should be treated as a friend to those who state it. Instead of viewing Tolerance as the end of what is acceptable, see it as the level at which you insist on being involved in using your influence and decision-making.
A good trainer will say, “This is what I want you to do; get back to me if you have any problems.”
But a better trainer will say, “This is what I want you to do; get back to me if you (set tolerance criteria here)” That way, the trainer is not used as a crutch for every small learning/development problem but allows the learner to make small mistakes and learn to fix them…but know when to escalate to the tutor when their learning has reached a ‘log-jam’.
Tolerance is a powerful technique built into PRINCE2 under the management by exception technique. It is powerful but simple to comprehend; a plus and a minus limit are placed around a management control limit, such as cost, with the project manager giving the regular highlights reports to the project board.
As long as the project or stage remains within Tolerance, no action or decision must be made. But directly, the project manager forecasts that Tolerance is to be exceeded, which triggers an exception report’s raising. The project manager uses the process to escalate issues and risks to create the exception report and bring it before the Project Board.
This means that the project board must place trust in the regular highlight reports and assume that they contain accurate information. But this is where project assurance can play an essential part by auditing and checking the data.
The tolerance limits for positive and negative ranges do not need to be the same, and frankly, are typically different (think of your family budget – is the overspend limit where you need to take action, the same as the underspend limit where you need to suggest the use of available funds? Probably not)
Project level tolerance is first set at the Starting Up a Project process. and influences both the project approach and the content of the Project Brief.
Although not stated in the PRINCE2 Manual, all tolerances must emanate from the Business Case. I will discuss in this article that time, cost, scope, quality, risk, sustainability and benefits all impact the business case, and hence this vital document should be used as the starting point for any tolerance decisions.
There is a temptation by novice project boards to set tight tolerances as they do not trust the project manager, but this is a mistake since tight tolerances are easily triggered by minor deviations causing many exception reports to be raised and increasing involvement by the project board.
PRINCE2 7Tolerance Application
The most common tolerances are time and cost (and we will cover the other types later in this article).
Here is a helpful diagram showing a graph of time and cost tolerance:

Note that a forecast of any value that deviates outside the tolerance ‘box’ will trigger the need to create an Exception Report sent to the next management level. The following diagram shows just four examples of where this would be true:
The typical human problem is that individuals must be more open about time and budget spending once a project is underway. In particular, at a mid-point within a stage, if spending has been higher than initially planned, the forecast is to be reduced so that the original time and cost limits can still be met.
At each reporting period, the team successively reduces the remaining time/cost in the mistaken and optimistic belief that they can ‘make up/reduce’ the overspend/delay and thus keep the forecast within tolerance bounds. The project manager uses the process report highlights to create the highlight report and include the status of both tolerance levels and projections.
As the end of the stage approaches, the actual spending shows that Tolerance has been exceeded. It is now too late to fix the problem’s root causes.
The problem here is not in the PRINCE2 method of Tolerance but the application of allowing optimism and wishful thinking on behalf of the team, in that they always ‘believed/hoped’ that the final time-part of the stage would underspend or come in early (“Hey! Surely we are getting more efficient?”) and so keep the stage within tolerance bounds.
The PRINCE2 Manual describes how a tolerance corridor can be shown graphically so that at any given point, if it is forecast, the tolerance corridor will be exceeded (even though the stage is still predicted to be completed within Tolerance), an exception report is raised.
The following diagram demonstrates this principle:

When starting a tolerance corridor at the start of a stage, problems can arise from the fact that the corridor is very narrow at the beginning of the management stage (see above), so deviating outside of it can quickly occur – causing the unnecessarily high frequency of exception report/regular and inappropriate project board involvement.
The way to get around this is to agree to introduce it (say) one-third through the stage, or (better, in my opinion) to use only the end tolerance as a trigger for (say) the first third of the stage and then introduce the time corridor.
Note: PRINCE2 advises that a change budget and risk budget may also be set in addition to a stage budget.
Be clear. The stage budget is what you are applying Tolerance against.
The change budget is a separate ‘pot’ and can only fund any changes. Such spending will need the agreement of the project board or a change authority if one has been agreed upon and set up. Tolerance is not applied here. If you have no changes, then the change budget is returned. It is not used to fund any ‘deviations’!
Risk Budget
Similarly, this budget is only available for risk actions and management. If it is not used, then it is returned. Tolerance is not applied here.
It is worth reminding ourselves of the different levels that Tolerance can be set within a typical PRINCE2 project:
- Project level tolerance
- Stage level tolerance
- Work Package tolerance (optional)
Corporate/Programme Management will set and agree on the project-level Tolerance, and the Executive will be held to account for such Tolerance. They will then ‘manage by exception’ with the project board and have very little involvement – safe in the knowledge that if such Tolerance is forecast to be exceeded, the Executive will bring this fact to their immediate attention.
The Project Board (and ultimately the Executive) will set stage-level tolerances at each end-stage assessment. This uses the authorize a stage or exception plan process. This is a ‘contract’ with the project manager to manage the stage daily.
The project board will then ‘manage by exception’ with the project manager and have very little involvement apart from reading the regular Highlight Reports issued by the project manager– safe in the knowledge that if such Tolerance is forecast to be exceeded, then the project manager will bring this fact to their immediate attention.
During the controlling stage process, the project manager will monitor, manage and control the stage within tolerance bounds.
Optionally, the project manager can set a tolerance at the work package level. This is then a ‘contract’ of understanding between the project manager and the team manager/team member(s) using the authorizing a work package process and the accepting a work package process.
The project manager will state the Tolerance in the work package itself. When the team accept it, they will create the specialist products issuing a Checkpoint Report to the project manager at a frequency laid down in the work package.
Note that if Tolerance is forecast to be exceeded, the team manager raises this as an Issue on the issue register, bringing this to the attention of the project manager, who will now consider the deviation within the more extensive remit of the stage and decide on the following steps to take.
Whatever the level of Tolerance, once it is forecast to be exceeded and an Exception Report is created, this will include a list of options for recovery and a recommendation from the report creator.
Many potential decisions may be taken, but the following is a good list of possible responses to the Exception Report:
- Accept and request implementation of one of the Exception Report options
- Upon reading, request implementation of their own (additional) option
- Delay a decision until a later time point
- Delay a decision pending further requested information
- Reset a (higher) level of Tolerance and continue as before
- Escalate it to the next level to first receive advice/guidance
- Prematurely close the project (the Project Board only)
Consideration must be given at the appropriate planning time for the type and deviation amount of each tolerance set. But of course, there is another set of variables here – and probably the most important of all, the type or control areas of Tolerance used.
The Six Types of Tolerance (ALL should be considered when planning)
Any one or more in combination may be used.
Time
Most commonly used, as many projects are end-date driven. If a critical end date is set, the project manager would want to produce a plan that shows an earlier start time and/or total duration so that the planned finish time is before the driven end date and a positive time tolerance showing an on-date project completion.
If this is not done, a positive time tolerance of zero must be used. This should be entered into the risk register as a risk with appropriate actions and proximity data for timely resolution if needed.
Cost
Time and cost are naturally linked; for example, taking longer leads to additional resource costs.
Project Boards are often mesmerized by ‘budgets’ and set miserly tolerances to protect themselves rather than digging into the Business Case. They should be looking at profit margins, doing best-case/worst-case scenarios, and then at sensitivity analysis.
This will help build a clear picture of the plus and minus zone where they must get involved.
Using these control metrics rather than ‘what is the worst we can tolerate’ – by then, it’s too late, will move them forward to sensible cost tolerances.
Scope
This needs careful thought and is often a more sensible tolerance choice than cost or time. As an approximation, consider scope as similar to functionality or requirements. It also has a knock-on effect on quality; for example, the scope includes plastering if the wall needs to have a smooth plaster finish.
So, in summary, scope tolerance relates to what products are ‘must have’ and what are ‘nice to have’ (using the ‘MOSCOW’ approach), but it also relates to what activities the project plan includes. For example, you might agree that ‘plastered wall’ is an included product, but the plan may include consultation with wall plastering specialists…
DSDM Atern or Agile projects are worth mentioning, whereby the team are driven to deliver what they can within a given time limit. This, by definition, infers that the deliverables will be de-scoped if needed to provide what they can within a time box.
Put simple, scope tolerance infers setting the limits within the choice of a minimum to include the ‘must haves’ and a maximum of the ‘nice to haves’
Quality
Setting tolerances by quality will be defined in the product description quality tolerance or in allowable deviations within the Project Product Description.
Be clear. Quality tolerance does not mean ‘poor quality’. A simple analogy might be preparing a meal for your friends. Fresh produce may be the criteria or the choice of a vegetarian option or the selection choice of several dishes.
None of these options includes poor raw materials, inept cooking techniques or sloppy presentation.
For the above reasons, quality can be synonymous with the old classic “fitness for purpose,” which immediately suggests a range that can be used for quality tolerance.
Risk
The two main parameters of a risk are the probability and its impact on the project meeting the project objectives. Two other parameters which may come into play in defining risk tolerance are a risk’s severity and proximity.
Setting risk tolerance along these lines makes sense, where a plus and minus value for the above can be used.
It might be a more blunt approach where a named risk or set of risks cannot be tolerated if their probability or impacts rise above a pre-set value.
Consider entering a new marketplace whose project represented a significant financial commitment and a major player was also considering joining the same market.
Suppose it looks greater than (say) 50% that they will enter (market intelligence could be used here). In that case, the project may have to be re-scoped (to include added value functionality so that you have improved competitive sales revenue), or you withdraw and cut your losses.
Benefits
These are the business benefits in the Business Case and the Benefits Management Approach.
This is one of the main reasons I talked of the business case being a prime driver for Tolerance.
A PRINCE2 Business Case must include the benefits (and dis-benefits) of tolerance bounds derived from best-case and worst-case scenarios. These will provide the critical tolerance control metrics where the project board must be involved so that they may make informed choices.
Again, don’t set these metrics at the best or worst-case point – it will then be too late!
PRINCE2® 7 Foundation and Practitioner


Learn PRINCE2® 7 Foundation and Practitioner Online
** Enhance your PRINCE2 career now **
PRINCE2® Masterclass gives you the skills necessary to manage projects effectively and achieve your objectives.
Get 7 days a week 12 months one to one coaching with ex PRINCE2 examiner Dave Litten.
PRINCE2® is a globally recognized project management framework. By completing both the Foundation and Practitioner courses through our self-paced e-learning, you will develop an understanding of the methodology and learn how to effectively adapt it to any project.
The PRINCE2® 7 Foundation and Practitioner Masterclass is PeopleCert Accredited and guarantees to take you from PRINCE2 Novice to PRINCE2 Practitioner with our famous video learning, study guides and practice exams.
What Does the Masterclass Cover?
The PRINCE2 Foundation examination assesses your knowledge and comprehension of the PRINCE2 project management methodology as detailed in the syllabus. The PRINCE2 Practitioner examination, on the other hand, gauges your ability to apply and tailor the PRINCE2 method. Candidates who pass the Practitioner exam should be able to start implementing the method on an actual project with some guidance. However, their effectiveness may differ based on their experience in project management, the complexity of the project, and the level of support they receive in their work environment.