PRINCE2 Foundation Exam Checklist – Part 2 

 April 3, 2023

By  Dave Litten

PRINCE2 Foundation Exam Checklist – Part 2

Controlling a Stage Checklist

You understand how this process gives out work assignments, checks progress on them and agree on their completion.

You understand how new issues and risks are dealt with

You understand how to check that the stage is progressing acceptably or, if it is going off track, either dealing with the problem or referring it to the Project Board.

You understand the purpose of a Work Package both as an instruction and a control.

You understand that a team may have one or more Work Packages within a stage.

You are familiar with the boundary between Controlling a Stage and Managing Product Delivery processes as a customer/supplier interface.

You are familiar with the fact that this process is used for each project stage.

You are familiar with the activities within the process in terms of the purpose of each and what management products each involves

You appreciate that the Controlling a Stage process will trigger the Managing a Stage Boundary process either to prepare for an end-stage assessment or, as a result of an exceptional situation, where the Closing a Project process may be triggered instead.

Managing Product Delivery Checklist

You understand the Managing Product Delivery Work Package statement and objectives.

You appreciate that a team may work on more than one Work Package within a stage, that there may be more than one specialist team, and that the Managing Product Delivery process may be used several times during a management stage.

You appreciate that the Work Package provides instructions to build one or more products and includes a copy of each relevant Product Description. 

You appreciate that this process covers the work of the Team Manager, not the Project Manager, but if an individual is not available, the Project Manager may fill both roles.

You understand using the Work Package as the Project Manager control mechanism.

You are aware that the “Execute a Work Package” activity covers the creation and testing of the specialist products and that the Quality Review is a type of test. Therefore that this technique would be used within this activity.

You’re aware that the results of a Quality Review are entered into the Quality Register along with any other less formal tests.

You understand why team Plans are optional and the reasons that govern their choice.

You know the Checkpoint Reports and their frequency are detailed within each Work Package.

You appreciate that the specialist team creating the products within a Work Package may be done by internal or external staff. As such, an external organization may not need to be aware of nor use the PRINCE2 method.

You understand the purpose and use of the Highlight Report that the Project Manager creates and sends to the Project Board and others as laid down within the communications management approach.

You know the difference between project management actions covering the “Take corrective action” and “Escalate issues and risks” activities.

You are familiar with tolerance and its influence on whether an issue should be escalated to the Project Board or dealt with by the Project Manager.

You are familiar with the formal and informal use of issues, including the use of the Issue Report and the information it contains

 Managing a Stage Boundary Checklist

You have a high-level understanding of how this process is used to look back, determine where the project is now, and then look ahead for the forecast.

You understand the purpose and objectives statements for this process. 

You understand how this process interacts with the PRINCE2 principles and themes. 

You can explain the two triggers of Managing a Stage Boundary process. 

You appreciate that this process is not used within the last stage of a project but rather that the Closing a Project process is triggered in its place. 

You fully understand the activities within this process, their suggested sequence, and who is doing what within each activity. This is usually the Project Manager.

You understand which management products are used as input into this process and which products are being created.

You appreciate that an exception Plan may include an adjusted project Plan, possibly several team Plans, or a revised stage Plan.

You understand the relationship between using this process at the end of a stage or part-way through the management stage due to an exception.

You understand why if an exception Plan is requested, it will only need to cover future work within the stage rather than the work already covered, as this will have been closed down with an accompanying End Stage Report.

Closing a Project Checklist

You can identify the Closing a Project process objectives and the purpose statement.

You understand the five activities within this process, what happens in each and who is responsible. The individuals will typically be the Project Manager with Project Assurance but may also include Project Support. 

You understand how the Closing a Project process uses the management products that feed into it. 

You understand the purpose of the End Project Report as the Project Manager’s record of the project performance and final metrics. 

This process compares achievements against the original baselined Project Initiation Documentation (PID) and the latest PID version. 

You are familiar with the two triggers for this process; able to recognize when the last stage is complete from the Controlling a Stage process or as a Project Board instruction to close the project prematurely. 

You understand that the Project Board can instruct a premature close at any time via the “Giving ad hoc direction” activity because they chose not to authorize the remaining stage work or ordered project closure from their activity “Authorize a Stage or Exception Plan.” 

You understand that the Project Manager is responsible for closing the project and preparing information, such as the End Project Report for the Project Board. 

You know that any benefits realized at this point must be measured and reported. 

You understand there is no End Stage Report for the final stage as this is replaced by the End Project Report covering the whole project, including the last stage. 

You understand the details of the activity and follow an action recommendation as a mechanism to pass non-project work on to those responsible for the operational use of the final product. 

You can relate how this process associates with the Seven PRINCE2 principles.

PRINCE2® 7 Foundation and Practitioner

5.0
Prince2 Practitioner Masterclass
Prince2 Axelos Peoplecert Trademark Copyright

Learn PRINCE2® 7 Foundation and Practitioner Online

** Enhance your PRINCE2 career now **

PRINCE2® Masterclass gives you the skills necessary to manage projects effectively and achieve your objectives.

  • Optional:   Official Online Exam
  • Course type: E-learning
  • Duration: Approx 45 hours
  • Delivery: Online

Get 7 days a week 12 months one to one coaching with ex PRINCE2 examiner Dave Litten.

PRINCE2® is a globally recognized project management framework. By completing both the Foundation and Practitioner courses through our self-paced e-learning, you will develop an understanding of the methodology and learn how to effectively adapt it to any project.

The PRINCE2® 7 Foundation and Practitioner Masterclass is PeopleCert Accredited and guarantees to take you from PRINCE2 Novice to PRINCE2 Practitioner with our famous video learning, study guides and practice exams.

  • Overview

  • Objectives

  • Exam information

  • Duration

What Does the Masterclass Cover?

The PRINCE2 Foundation examination assesses your knowledge and comprehension of the PRINCE2 project management methodology as detailed in the syllabus. The PRINCE2 Practitioner examination, on the other hand, gauges your ability to apply and tailor the PRINCE2 method. Candidates who pass the Practitioner exam should be able to start implementing the method on an actual project with some guidance. However, their effectiveness may differ based on their experience in project management, the complexity of the project, and the level of support they receive in their work environment.

  • Prepare for your PRINCE2 7 Foundation and PRINCE2 7 Practitioner Exams with our famous on-line course with streaming HD Video Lessons, PDF study guides and Mock Eams. 
  • We are a PEOPLECERT (AXELOS) Business Partner – Our PRINCE2 Masterclass is fully certified for PRINCE2 7th Edition Foundation and Practitioner.
  • Bite Sized Lessons  The sheer size of PRINCE2 can be daunting. The Masterclass will guide you through the syllabus in easy to consume bite sized lessons
  • Enjoy yourself!  This PRINCE2 Foundation & Practitioner online course is broken into bite-size lessons, combining leading edge multimedia and interactive exercises for optimum enjoyment and knowledge retention
  • Take your time  Study at your own pace by bookmarking your progress and picking up where you left off at a speed that suits you
  • Be prepared and confident for the exams  Test your knowledge in a fun, entertaining environment with the PRINCE2 Foundation & practitioner exam revision tools
  • In the last 20+ years we have had 9,000+ Academy students successfully transform their careers as PRINCE2 Practitioners.

Dave Litten


Dave spent 25+ years as a senior project manager for UK and USA multinationals and has deep experience in project management. He now develops a wide range of Project Management Masterclasses, under the Projex Academy brand name. In addition, David runs project management training seminars across the world, and is a prolific writer on the many topics of project management.

Your Signature

{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}
Insert Content Template or Symbol

Join NOW!

Boost Your Career Now!

15% Discount on all courses with Coupon Code - PROJEX15