Business Case – create the full version and assemble the Project Initiation Documentation

During Starting Up a Project, an outline Business Case was created which formed part of the Project Brief. As a result of creating the Project Plan and planning in detail, the Business Case can now be updated with the full details.:
The project time-scale and the timing of benefit reviews, the cost of the project and the costs of operational and maintenance activities can now be added to the Business Case. Also the aggregated risks from the updated Risk Register can be summarised in the Business Case.
This full Business Case (which is owned by the project board executive), will be used by the project board to authorise the project in the first place, and used throughout the project to ensure that the project is and remains viable.
The Project Brief should be checked to see if there are any corporate or programme management standards concerning the format and content of the Business Case, in which case he should be applied.
Lessons from similar previous projects relating to business case development should be sought and applied, although some of these may already have been captured in the Lessons Log.
Business Case contents
The content of the detailed Business Case will now need to be added and will include:
- Costs and timescales extracted from the Project Plan
- Major risks that affect the viability of the project should be extracted from the Risk Register
- The expected benefits to be realized, and this needs to include any dis-benefits to ensure that the Business Case is balanced and realistic. Each benefit should include any related tolerances.



It is at this point that the Benefits Management Approach should be created/refined and the benefits from the detailed Business Case used here. Information regarding how each benefit is to be achieved and measured must be added including the timing of benefit reviews.
These benefit reviews may often align with End Stage Assessments, although these benefit reviews will continue after the project has completed.
Project assurance will review the draft Business Case and the project board should approve it and the Benefits Review Plan, although they may prefer to review them later as part of the Project Initiation Documentation.
Assemble the Project Initiation Documentation.
The Project Initiation Documentation is now assembled and consists of the nine approach documents, the project controls and Project Plan, and the full Business Case. The PID may not be one single document but a collection of documents.

This version of the PID created during the initiating a Project process will be used to gain authorisation for the project, and should be baselined and preserved as a record of what was originally agreed.


Project Assurance and the project board must now review and approve the PID. This will occur at the activity ‘authorize the project’ within the Directing a Project process.
For more information on passing your PRINCE2 Exams – CLICK HERE
PRINCE2® 7 Foundation and Practitioner


Learn PRINCE2® 7 Foundation and Practitioner Online
** Enhance your PRINCE2 career now **
PRINCE2® Masterclass gives you the skills necessary to manage projects effectively and achieve your objectives.
Get 7 days a week 12 months one to one coaching with ex PRINCE2 examiner Dave Litten.
PRINCE2® is a globally recognized project management framework. By completing both the Foundation and Practitioner courses through our self-paced e-learning, you will develop an understanding of the methodology and learn how to effectively adapt it to any project.
The PRINCE2® 7 Foundation and Practitioner Masterclass is PeopleCert Accredited and guarantees to take you from PRINCE2 Novice to PRINCE2 Practitioner with our famous video learning, study guides and practice exams.
What Does the Masterclass Cover?
The PRINCE2 Foundation examination assesses your knowledge and comprehension of the PRINCE2 project management methodology as detailed in the syllabus. The PRINCE2 Practitioner examination, on the other hand, gauges your ability to apply and tailor the PRINCE2 method. Candidates who pass the Practitioner exam should be able to start implementing the method on an actual project with some guidance. However, their effectiveness may differ based on their experience in project management, the complexity of the project, and the level of support they receive in their work environment.