PRINCE2 7 Product Checklist – the answer to project product control
You can become a more competent project manager or team member when you have grasped how vital and effective the Product Checklist is. If you have ever stumbled in your attempts to estimate and forecast activities within a project, then read on.
Let me start at the beginning. Suppose you want to estimate the effort needed to create a product, say a Power Supply Unit (PSU). Let’s imagine this is part of the design for the New Amplifier project.
You call the team in for a planning meeting to create your PRINCE2 Stage Plan (where the PSU will be designed, built, tested and approved.
Old School thinking (pre-PRINCE2)
This would have you estimating all the tasks/activities, assigning resources, getting the plan agreed upon, and starting work on the PSU…
The trouble starts to rear its ugly head once work proceeds. Let’s say a week has passed, and you want an update from the team on the progress being made for the new PSU:
Let’s assume the team have three activities that they have been working on:
- Create a prototype design schematic.
- Build prototype PSU
- Test prototype PSU
The team advise that:
- The schematic has been created and is at version 1.3
- The prototype is currently being built, and the team are 50% complete
- Some testing has been done – estimated at 10% complete
- The team have booked 16 hours so far
- You note that duration, work effort, and cost percentage complete have different percentage values
A week later, the team advised that they were behind schedule and give you an update on the percentage complete. You asked for an estimate for when they will finish and reported back should be done by the end of the week. Are you confident about that? Sounds Familiar?
Who is to blame for this?
Well, nobody, yet everybody!
Let’s go back to the beginning and consider the potential problems in that planning meeting.
Planning Problems
- The first problem was that you planned using activities only.
- The second problem is that you should have included product completion milestones, including those leading to product completion.
- The third problem was that ‘percentage complete’ is ambiguous and unnatural for humans! So let’s see how this can be improved:
Product-based Planning.
Of course, you were anticipating I would bring this up. Still, I’m not going to explain how to do it all, as I have written several articles and posted YouTube videos on this powerful technique already.
But I will remind you that during planning, a simplified summary of Product-based planning would be:
- Identify the products (both specialist and management) to be created
- Identify the activities required to develop each product
- Assign available resources to carry out the activities
- Create a schedule of critical dates
- Use this schedule to keep track of progress.
Okay. So a product is something that is produced and is usually tangible. An activity is just doing the required work to create the product. Work is not concrete – only the outcome of such work.
The Completed Product.
Quality is essential here.
Let’s re-live some horror stories:
- “But you said you needed a PSU – I thought you meant similar to the last one I made for you.”
- “You didn’t tell me it had to weigh less than one kilogram and have specific dimensions.”
- “I never agreed to test it – I thought you would do that.”
- “Now is a fine time to tell me it has to meet these country-specific safety standards.”
You get the idea that one person’s definition of ‘finished’ may differ from yours or your customer/user’s.
The Product Description.
PRINCE2, therefore, states that this be written as soon as possible after the need for the product has been agreed upon. It will contain the quality criteria that the product must meet and the key individuals involved. It will lay out the range of tolerances between which the quality criteria must fall.
Then, and only then, can the project manager and their team create steps 1 to 5 above. But now you have complete control, let me explain.
The PRINCE2 Product Checklist.
Amazingly, the PRINCE2 Manual says this is optional – but I say it is vital and should always be used. The critical discipline it gives is:
- Ensure that a Product Description has been drafted AND approved (and this means that the above quality criteria have also been approved). So everyone has a joint agreement on what ‘doneness’ looks like!
- A Work Package is given out and agreed to the team so that work can start work.
- The Product Checklist lays down the key planned and actual dates (which gives you variances to the plan if they occur)
- These planned and actual dates are given For Each Step In The Product Of Each Product, that is, the duration to create the first draft (prototype) of the product, The dates of the Quality Check to be carried out, the date that the product was approved, and if relevant, the date that the product was handed over to those who will now use it.
Product Checklist Layout
A suggested layout may look something like this:

The power of the PRINCE2 Product Checklist:
- It gives you an agreement on what the product will be, including its quality criteria (this would often include its functionality or performance criteria)
- This level of detail allows far more accurate estimates for the duration, work effort, resources, and tracking.
- Each product/sub-product is only complete when approved – no margin for error.
- Using tracking techniques such as actual/remaining work is better than percentage complete, but whichever method is used, you will have far more control over successful project and product delivery.
Do you want to pass your PRINCE2 Foundation and Practitioner Exams with our PRINCE2 Masterclass?
PRINCE2® 7 Foundation and Practitioner


Learn PRINCE2® 7 Foundation and Practitioner Online
** Enhance your PRINCE2 career now **
PRINCE2® Masterclass gives you the skills necessary to manage projects effectively and achieve your objectives.
Get 7 days a week 12 months one to one coaching with ex PRINCE2 examiner Dave Litten.
PRINCE2® is a globally recognized project management framework. By completing both the Foundation and Practitioner courses through our self-paced e-learning, you will develop an understanding of the methodology and learn how to effectively adapt it to any project.
The PRINCE2® 7 Foundation and Practitioner Masterclass is PeopleCert Accredited and guarantees to take you from PRINCE2 Novice to PRINCE2 Practitioner with our famous video learning, study guides and practice exams.
What Does the Masterclass Cover?
The PRINCE2 Foundation examination assesses your knowledge and comprehension of the PRINCE2 project management methodology as detailed in the syllabus. The PRINCE2 Practitioner examination, on the other hand, gauges your ability to apply and tailor the PRINCE2 method. Candidates who pass the Practitioner exam should be able to start implementing the method on an actual project with some guidance. However, their effectiveness may differ based on their experience in project management, the complexity of the project, and the level of support they receive in their work environment.