How Do I Change a Task’s Start and Finish Dates in Project 2010?
If a Task is Auto Scheduled, you leave Project to calculate Start and Finish dates. If you attempt to override these calculated dates, Project applies a Task Constraint based on the dates you enter. If a Task is Manually Scheduled, you can enter the Start and/or Finish dates yourself and Project schedules the task accordingly.
Dave spent 25+ years as a senior project manager for UK and USA multinationals and has deep experience in project management. He now develops a wide range of Project Management Masterclasses, under the Projex Academy brand name. In addition, David runs project management training seminars across the world, and is a prolific writer on the many topics of project management.