.st0{fill:#FFFFFF;}

Business Case Justification in PRINCE2 7 

 April 3, 2023

By  Dave Litten

Business Case purpose

The Business Case determines whether the project is, and remains, desirable, viable and achievable. It answers, is the investment in this project still worthwhile?’

An outline Business Case is created within the Project Brief to determine if it is worth investing in the initiation stage. The detailed Business Case forms part of the Project Initiation Documentation and is used by the project board to determine if we have a worthwhile project.

The Business Case is used and updated throughout each stage with current information to determine if the project remains viable. If the Business Case ceases to be feasible, then the project should be changed or stopped.

The output of a project is the specialist products; the outcome is the result of the change derived from using the project outputs, and the benefit is a measurable improvement resulting from an outcome seen as an advantage by at least one of the stakeholders.

Usually, the outcomes and benefits of the project are realized after the project has been completed. However, some projects can use a phased delivery where some products are released into the operational area, and benefits may accrue during the project’s life.

PRINCE2 Business Case approach

The PRINCE2 approach to the Business Case is that it first must be developed, meaning it contains the correct information; verified, meaning that the project is still worthwhile; maintained, indicating that the business case is updated with actual costs and benefits for both current and forecast time-frames; confirmed, meaning assessing whether the benefits have been, or will be realized.

The project board executive is responsible for the Business Case; however, its development, as above, may be delegated to the project manager or someone else with appropriate finance knowledge and skills, including the business assurance role, if the executive has delegated their responsibilities.

The Business Case will be reviewed at the end of the Starting Up a Project and again at the end of the Initiating a Project processes and will form part of the evidence for the project board to decide what to do next. During a stage and as part of any impact assessment for issues or risks, the Business Case should be checked to see the impact.

At the end of each stage, the project manager will update the Business Case based on the next Stage Plan and updated Project Plan, and this will be presented to the project board for them to decide what to do next.

The investment appraisal section of the Business Case provides the project will with information to verify that it justifies the authorization and continuation of the project.

The Senior User is responsible for specifying the benefits within the business case and will be held to account by corporate or programme management that the forecast benefits are eventually realized.

The Benefits Management Approach is created from the detailed Business Case during the initiation stage, and this will be updated at the end of each management stage as part of the evidence for the project board to consider whether to proceed. The project’s Benefits Management Approach defines the scope, timing and responsibility for several reviews of the expected benefits.

Each End Stage Report should include the benefits that can be measured during a project.

The purpose of the PRINCE2 Business Case Theme

It is to establish mechanisms to judge whether the project is (and remains) desirable, viable and achievable as a means to support decision-making in its (continued) investment.

The PRINCE2 Business Case Development Path

Develop – getting the correct information such that decisions can be made.

Verify – assessing whether the project is (still) worth doing.

Maintain – updated with the latest actual/forecast costs and benefits

Confirm – assessing whether benefits have, or will, be realized.

The PRINCE2 project should not include products that do not directly or indirectly enable the realization of benefits.

Wherever possible, benefits should be expressed in tangible ways.

The quantification of benefits enables benefits tolerance to be set, and the measurability of the benefits ensures they can be proven.

Investment Appraisal.

This compares the aggregated benefits and dis-benefits to the project costs (extracted from the Project Plan) and ongoing incremental operations and maintenance costs for a PRINCE2 project.

May use techniques such as:

Through-life costs
Net benefits
Return on Investment (ROI)
Payback period
Discounted cash flow
Net present value
Sensitivity Analysis
Internal Rate of Return

The Benefits Management Approach.

Used to define how and when a measurement of the achievement of the project’s benefits expected by the Senior User can be made. It contains the following information:

The scope of the Benefits Management Approach and details of the benefits that are to be measured
Who is accountable for the expected benefits
How achievement of the expected benefits are to be measured
When the expected benefits can be measured
What resources are needed for the review work
Baseline measures against which the improvements will be calculated
How the performance of the project’s product will be reviewed

End Stage Report – the steps to its creation

The PRINCE2 process Managing a Stage Boundary is used to prepare for an end-stage or an exception assessment. For this article, I will only concentrate on all the former.

The purpose of an end-stage assessment is to provide the project board with sufficient information to make an informed choice about whether to proceed with the project or not.

Before discussing the content of an end-stage report, it is, therefore, essential to understand the sources of information that will be included. It makes sense to first look at the activities within the Managing a Stage Boundary process.

Managing a Stage Boundary

The following diagram shows the typical route:

Managng A Stage Boundary
Business Case Justification in PRINCE2 7 1

Business Case Justification

When the project manager sees the current stage nearing completion, he will refer to the Managing a Stage Boundary process as above.
The first step this to create the next stage plan, which will be drawn from the top-level details within the project plan.

The Stage Plan

Using the PRINCE2 product-based planning technique, these top-level details will be decomposed into a detailed level suitable for day-to-day management within the next stage.

The project manager will want to involve as many appropriate and relevant people as possible to create a robust and achievable stage plan. In particular, specialists, team members, senior suppliers, and project assurance should be involved in creating the next stage plan.

The project initiation document should be referenced, particularly for the relevant standard documents, since risk, quality, configuration management, and communication aspects of the project will heavily influence the next stage plan.

As part of Product-Based planning, new products will be identified. These may consist of further refined existing products or entirely new products. Whichever the case may be, new product descriptions and their relevant quality criteria will need to be created. The quality register will need to be updated with the relevant information to carry out quality checks within the next stage.

Also, configuration item records will need to be created or modified for each new product to track the status of that product.

As part of planning for the next stage, new or modified risks may be identified, and these, too, will need to be entered into the risk register and their appropriate response actions included within the next stage plan. Similarly, any ongoing issues and their actions may need to be included within the stage plan (unless they are currently being dealt with).

As a consequence of creating a more detailed next-stage plan, the project plan will likely need to be updated and refined. There are several reasons for this:

  1. The newly created next-stage plan will typically have a different stage end date, cost, products, and resources than those estimated initially within the project plan.
  2. Since the current stage is coming to a close, information such as products, cost, and end dates will need to be entered into the updated project plan.
  3. The business environment may have changed since the project initiation document was signed off. For example, the user group may have different objectives, or market forces may have changed.

Once the project plan has been updated, the business case must be updated to ensure that the project is still providing continued business justification. For example, project or operational costs may rise, schedules may be delayed, or new competitors may have arrived, and hence the end product may need to be modified or enhanced.

Typically, the project manager and the Project Board executive will review sections of the business case and update them as necessary.
Similarly to the above, the project manager and executive should review the organization’s risk appetite and the overall risk situation to ensure it remains within risk tolerances.

They should also review the benefits management approach to ensure there has been updated that the results of any benefit reviews that may have taken place and that such results should be compared with the expected results. Similarly, any planned benefit reviews are included in the stage and project plans.

All of the above culminate in the creation of the End Stage Report as shown in this activity:

Business Case Justification

In the report stage end activity, the end stage report will be created, which will be reviewed by the project board along with the other outputs of the Managing a Stage Boundary process to decide whether to proceed to the project’s next stage.

As you can see in the diagram above, the project manager may create a lessons report, mainly if specific lessons should be applied to the remainder of this project or would be helpful to other projects.

It might be helpful to remind you of the content and structure of a lessons report:

Lessons Report
Executive summary
Scope (project or stage)
What went well, what went poorly, plus any recommendations?
Should cover:
project management method
specialist methods used
project strategies
project controls
any abnormal events
Review of any valuable measurements such as:
the effort to create products
effectiveness of the Quality Management Approach.

Important lessons may be clarified with details on the following:
details of the event and its effect/impact
causes or trigger
early-warning indicators
recommendations
Was the triggered event identified as a risk?


Writing a PRINCE2 Business Cаѕе

Project Documentation Overview

A Project Brief outlines what needs to be accomplished

The Project Plan details how to achieve those goals

The Business Case explains why the project is necessary

In PRINCE2 methodology the Business Case is the projects driving force.

Senior management reviews it before authorizing each project stage It serves as a benchmark for measuring progress

Any changes to the Project Plan must be evaluated based on their impact on the Business Case

Without a Business Case projects cannot proceed

PRINCE2 Business Case Structure

Business Case Justification In Prince2 7 Business Case Justification
Business Case Justification in PRINCE2 7 2
Business Case Justification In Prince2 7 Business Case Justification
Business Case Justification in PRINCE2 7 3
Business Case Justification In Prince2 7 Business Case Justification
Business Case Justification in PRINCE2 7 4

The Business Case justifies the investment in a project by highlighting its benefits It consists of eight key sections

Reasons

Explain why the project is necessary
Align with corporate/programme strategy
Address specific needs (eg improving customer satisfaction boosting profits updating outdated systems)

Options

Present different approaches to address the identified need
Justify why the chosen option (the project) is the best solution
Demonstrate thorough consideration of alternatives

Benefits

Persuade stakeholders of the projects value
Include both tangible and intangible benefits
Provide evidence and detailed projections to support claims

Risks

Identify main risks to project success
Be transparent to gain management confidence
Demonstrate foresight and realism

Costs

Present the total projected cost
Justify each area of expenditure
Provide an accurate budget forecast

Timescale

Outline the project duration
Detail activities and goals for each stage
Explain the rationale behind the proposed timeline

Investment Appraisal

Compare costs and benefits
Demonstrate the projects value for money
Quantify return on investment over a fixed period

Evaluation

Objectively assess your own Business Case
Highlight the strongest and most certain benefits
Reinforce why the project is necessary and the best approach

By thoroughly addressing these elements the Business Case provides a comprehensive justification for the project enabling senior management to make informed decisions about its approval and ongoing support

For more information, CLICK HERE

PRINCE2® 7 Foundation and Practitioner

5.0
Prince2 Practitioner Masterclass
Prince2 Axelos Peoplecert Trademark Copyright

Learn PRINCE2® 7 Foundation and Practitioner Online

** Enhance your PRINCE2 career now **

PRINCE2® Masterclass gives you the skills necessary to manage projects effectively and achieve your objectives.

  • Optional:   Official Online Exam
  • Course type: E-learning
  • Duration: Approx 45 hours
  • Delivery: Online

Get 7 days a week 12 months one to one coaching with ex PRINCE2 examiner Dave Litten.

PRINCE2® is a globally recognized project management framework. By completing both the Foundation and Practitioner courses through our self-paced e-learning, you will develop an understanding of the methodology and learn how to effectively adapt it to any project.

The PRINCE2® 7 Foundation and Practitioner Masterclass is PeopleCert Accredited and guarantees to take you from PRINCE2 Novice to PRINCE2 Practitioner with our famous video learning, study guides and practice exams.

  • Overview

  • Objectives

  • Exam information

  • Duration

What Does the Masterclass Cover?

The PRINCE2 Foundation examination assesses your knowledge and comprehension of the PRINCE2 project management methodology as detailed in the syllabus. The PRINCE2 Practitioner examination, on the other hand, gauges your ability to apply and tailor the PRINCE2 method. Candidates who pass the Practitioner exam should be able to start implementing the method on an actual project with some guidance. However, their effectiveness may differ based on their experience in project management, the complexity of the project, and the level of support they receive in their work environment.

  • Prepare for your PRINCE2 7 Foundation and PRINCE2 7 Practitioner Exams with our famous on-line course with streaming HD Video Lessons, PDF study guides and Mock Eams. 
  • We are a PEOPLECERT (AXELOS) Business Partner – Our PRINCE2 Masterclass is fully certified for PRINCE2 7th Edition Foundation and Practitioner.
  • Bite Sized Lessons  The sheer size of PRINCE2 can be daunting. The Masterclass will guide you through the syllabus in easy to consume bite sized lessons
  • Enjoy yourself!  This PRINCE2 Foundation & Practitioner online course is broken into bite-size lessons, combining leading edge multimedia and interactive exercises for optimum enjoyment and knowledge retention
  • Take your time  Study at your own pace by bookmarking your progress and picking up where you left off at a speed that suits you
  • Be prepared and confident for the exams  Test your knowledge in a fun, entertaining environment with the PRINCE2 Foundation & practitioner exam revision tools
  • In the last 20+ years we have had 9,000+ Academy students successfully transform their careers as PRINCE2 Practitioners.

Dave Litten


Dave spent 25+ years as a senior project manager for UK and USA multinationals and has deep experience in project management. He now develops a wide range of Project Management Masterclasses, under the Projex Academy brand name. In addition, David runs project management training seminars across the world, and is a prolific writer on the many topics of project management.

Your Signature

{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}
Insert Content Template or Symbol

Join NOW!

Boost Your Career Now!

15% Discount on all courses with Coupon Code - PROJEX15