Authorize the project in PRINCE2.
During the initiation stage, the Initiating a Project process is used to assemble all the information within the Project Initiation Documentation. This documentation will normally be reviewed at draft status by project assurance, but when the project manager determines that this documentation is ready to be approved, then the project manager will request from the project board for them to authorize the project.
Also within the initiation stage, the project manager will trigger the Managing a Stage Boundary process to prepare the next Stage Plan, updates to other key documents such as the Business Case and the Project Plan and prepare an End-Stage Report. When the project manager is content that the draft documentation is ready for approval then the project manager will request from the project board to authorize the next stage. The activity used for this, is the Authorize a Stage or Exception Plan (within the Directing a Project process), will normally take place at the same meeting used to authorize the project.
Both of the requests to authorize the project and authorize a stage or exception plan will normally be performed in parallel, and often at the same meeting, since both the PID and the next stage plan needs to be signed off before the project can proceed to the next stage.
Authorize the project objectives.
The objective of authorize the project is to decide whether to proceed with the rest of the project, however if the project board decided not to proceed then the project should be prematurely closed, and in this case the closing a project process will be used followed by a request from the project manager to authorize a project closure by the project board.
In order to authorize the project the project board will need to undertake the following actions:
- Review the project definition and project approach to ensure that they are still feasible
- Check that lessons from previous projects have been incorporated.
- The project board will want to confirm that the four strategy documents are sufficient for the project and that they will perform their purpose of adequate control throughout the project.
- The project board must ensure that the project management team have agreed roles and responsibilities, in particular any delegation of duties for example the appointment of a change authority.
Authorize the project – product-based planning.
The project board will want to ensure that the Project Plan is viable and achievable and that the project controls are adequate for the type and nature of the project before a decision is made to authorize the project. As a result of planning the product based planning technique will have been used and the project board must review and approve all product descriptions. They will also want to check that the tolerances for the project set by corporate or programme management remain appropriate and realistic.
The Project Plan will identify resources needed to up the project, and the project board must satisfy themselves that they are able to obtain or commit these resources; however such resources will only be released to the project manager on a stage by stage basis, despite agreeing to the project plan in the authorize the project activity.
The PID in authorize the project.
The Project Initiation Documentation will also include how the PRINCE2 method is to be tailored to meet the needs of this particular project, and the project board must satisfy themselves that this tailoring is appropriate before agreeing to authorize the project.
As one of the final activities leading to full assembly of the Project Initiation Documentation, the outline Business Case will have been refined to become the detailed Business Case. The Project Plan timescales and costs will have been input to the detailed Business Case, and the project board must satisfy themselves that the Business Case demonstrates a viable project before commencing to authorize the project.
The Senior User role is responsible for identifying benefits contained within the Business Case, and the project manager will use these to draft the Benefits Review Plan showing how and when the benefits will be realized This also needs to be reviewed and approved by the project board as part of the authorize the project activity.
Authorize the project – project board decision.
The project board must now either authorize the project manager to deliver the project or instruct the project manager to close the project prematurely if they decide not to proceed any further as part of the authorize the project activity.
Whatever decision the project board make they must now notify corporate programme management plus other interested parties that the activity authorize the project has resulted in the project moving into its first delivery stage, or if more information is needed before taking a decision, or whether the project board have decided to prematurely close the project.
This course is DEPRECATED
The old PRINCE2 6th Edition Foundation and Practitioner syllabus was upgraded in 2024. Check out the brand NEW PRINCE2 7th Edition Masterclass, covering all the current syllabus, training material and online exam benefits HERE

Your Route To PRINCE2 6th Edition Practitioner
Study PRINCE2 6 Foundation and Practitioner Exams with our famous on-line course with streaming HD Video Lessons, study guides and mock exams. In the last fifteen years we have had 6,000+ Academy students successfully transform their careers as PRINCE2 Practitioners.
