PRINCE2 Walk Through – Step ONE
A PRINCE2 project can be standalone or part of a programme, in which case a project may be triggered from either those within a programme, here called programme management or by appropriate senior management within an organization, here called corporate management.
PRINCE2 Overview
Either of the above therefore triggers a PRINCE2 project by issuing a Project Mandate. This document should contain, as a minimum, the name of the prospective project board executive and the reasons for the need for the project.
As such, it may only be verbal instruction or an e-mail. Conversely, it could be the final report from a feasibility study. It must contain sufficient information provided by an appropriate authority level to trigger the first PRINCE2 process.
The first PRINCE2 process, Starting Up a Project, uses the initials SU. Starting Up a Project occurs pre-project and is used as a solid foundation before the first stage in a PRINCE2 project.
Developing detailed plans can consume many resources, and since many projects should not even be started in the first place, it makes sense for SU to be used as a ‘filter’ – both to prevent poorly conceived projects from beginning in the first place and to establish an understanding of the goals and objectives of the project. In particular, to ensure that there are good business reasons to proceed with the PRINCE2 project.
One of the first activities is to appoint the Executive of the PRINCE2 Project Board and the Project Manager; the Executive will now design and nominate the remaining roles within the Project Board, including who will fill the Senior User and Senior Supplier roles and how Project Assurance is to be handled.
The project manager will design and appoint any other supporting roles that will be needed, such as project support, configuration management and the optional Team Manager role.
Two main PRINCE2 management products are output from this process, the Project Brief and a plan for the Initiation Stage.
The Project Brief contains the outline Business Case with sufficient information to justify carrying out the initiation stage and creating the Project Product Description, which includes aspects such as the customer’s quality expectations and acceptance criteria for the project’s end product.
The Project Brief also contains the Project Approach management document. This lays out the approach used by the project to deliver the end product, for example, basing the design on an existing product or developing an entirely new product design, or whether or not resources used for the project will be provided internally or by the use of third parties.
The PRINCE2 Project Brief can be seen as a refinement of the Project Mandate. Similarly, the Project Brief will be refined further within the initiation stage to become the Project Initiation Documentation (PID).
A critical principle of PRINCE2 is that of management by exception. This aims to set tolerance levels at the directing, managing, and delivering management levels within a project. Tolerance is a limit within which a particular management level may manage without escalating to the next level above.
There are six PRINCE2 objectives against which tolerances may be set: time, cost, quality, scope, risk, and benefits. Suppose any of these tolerances are forecast to be exceeded. In that case, an Exception Plan must be raised, which, if approved, would replace the existing plan that would have no longer been completed within tolerance.
Corporate or Programme management has the authority to set PRINCE2 project level tolerances, the Project Board can set stage level tolerances, and optionally, the Project Manager may set tolerances around a particular Work Package.
One of the PRINCE2 principles is learning from experience. For this reason, the Lessons Log is created and filled with lessons that can be learned from appropriate individuals and previous similar projects. The project manager would be expected to collect such data proactively.
The Lessons Log will be updated and used throughout the PRINCE2 project, particularly as a source of information to create the optional Lessons Report at the end of each stage. The Lessons Report is created as part of the Closing a Project process. In this way, lessons can be passed on to future similar projects.
The Daily Log is also created by the project manager and is used as a ‘diary’ by the project manager for the remainder of the project. But here at SU, it is also used to capture any risks and issues that need to be managed before the formal start of the project.
To proceed any further, the newly formed project board will need to decide whether or not it is worth investing in creating the PID. In particular, how much effort and resources are required in the initiation stage?
In this way, poorly conceived projects can be nipped in the bud before further action is wasted upon them. The information in the Project Brief and the initiation Stage Plan will give the project board sufficient information to make an informed choice.
The Starting Up a Project process culminates with the project manager requesting that the Project Board authorize the initiation stage. This uses the first activity, ‘authorizing initiation,’ within the directing a project (DP) process.
The project board may decide not to proceed any further. However, based on the evidence above, let’s assume that, in this instance, they agree to invest in the initiation stage. This will become the formal start of the project, and corporate/programme management will be informed that the project has been initiated.
PRINCE2® 7 Foundation and Practitioner


Learn PRINCE2® 7 Foundation and Practitioner Online
** Enhance your PRINCE2 career now **
PRINCE2® Masterclass gives you the skills necessary to manage projects effectively and achieve your objectives.
Get 7 days a week 12 months one to one coaching with ex PRINCE2 examiner Dave Litten.
PRINCE2® is a globally recognized project management framework. By completing both the Foundation and Practitioner courses through our self-paced e-learning, you will develop an understanding of the methodology and learn how to effectively adapt it to any project.
The PRINCE2® 7 Foundation and Practitioner Masterclass is PeopleCert Accredited and guarantees to take you from PRINCE2 Novice to PRINCE2 Practitioner with our famous video learning, study guides and practice exams.
What Does the Masterclass Cover?
The PRINCE2 Foundation examination assesses your knowledge and comprehension of the PRINCE2 project management methodology as detailed in the syllabus. The PRINCE2 Practitioner examination, on the other hand, gauges your ability to apply and tailor the PRINCE2 method. Candidates who pass the Practitioner exam should be able to start implementing the method on an actual project with some guidance. However, their effectiveness may differ based on their experience in project management, the complexity of the project, and the level of support they receive in their work environment.