PRINCE2 Exception Report Creation


PRINCE2 uses the principle of management by exception, with tolerances set at each appropriate level, for example, project, stage, or work package levels, and the PRINCE2 Exception Report plays a vital role in this.
Also, the type of Tolerance is specified at each level. For example, time, cost, benefits, scope, risk, sustainability, or quality will be used in creating the PRINCE2 Exception Report.
A PRINCE2 Exception Report is created whenever a Stage Plan or Project Plan is forecast to exceed the relevant tolerance bounds. At the first instance of forecasting that Tolerance is to be exceeded, the project manager will log it as an issue in the Issue Register.


The Exception Plan
The next step is to create the exception plan (based upon the information contained within the PRINCE2 Exception Report, which the project manager writes to advise the project board that Tolerance is forecast to be exceeded as well as to present a range of options and recommendations outlining the actions to take to resolve the situation.
Based solely on information laid out within the PRINCE2 Exception Report, the project board may choose to:
Approve or reject the situation.
Defer deciding between until later.
Request more information
Brought a concession for the project manager to proceed without the need for any corrective action
Instruct the project manager to resolve the problem.
Give advice and guidance to the project manager.
Request an exception plan based on one of the options (theirs or the project managers)
Seek advice and guidance from corporate or programme management.
Instruct that the project be prematurely closed.
The format of a PRINCE2 Exception Report can be in the form of a document, an email, or another form of electronic communication, or it may be given verbally.
PRINCE2 Exception report content
Exception Report title.
This should describe an overview of the exception situation that is being reported.
Cause of the exception.
This describes the root cause of the deviation that led to this exception and departure from the current plan. The reasons for the forecast deviation must be clearly stated and analysed.
The project manager will want to inspect the issue register and its impact analysis to help determine the cause.
Also, the project manager should get advice for all appropriate stakeholders, such as the specialist team, the team manager, and the individual or group who raised or caused the issue in the first place as part of preparing their PRINCE2 Exception Report.
Consequences of the deviation.
Before any action or recommendations can be made, it must be first understood precisely what the implications for both the project and corporate or programme management are to make informed choices.
Such impacts must be determined from the perspectives of the business, customer, user, and supplier. The implications for the business case are of particular importance, and these must be considered.
Also, the impact on the overall project plan must have been calculated. A helpful checklist when determining such effects within the PRINCE2 Exception Report is to consider the six variables that would be involved in any project, such as:
- Costs
- Timescales
- Quality
- Scope
- Risk
- Benefits
Usual documentation to act as a reference within your PRINCE2 Exception Report to determine the impact are:
- The issue register
- Stage plan
- Work package
- Project initiation documentation
- Product checklist
- Quality register
The project manager will likely want to involve the specialist team in helping to describe such impacts and consider options for recovery or minimisation. Other applicable stakeholders to involve when creating the PRINCE2 Exception Report could be the users, customers, or appropriate operational managers.
PRINCE2 Exception Report Options
This lays down the options available to resolve the deviation and, for each option, what the effect would be on the business case, risks and tolerances. Several options for recovery should be given wherever possible, as this will provide the project board confidence that sufficient thought has gone into considering all possibilities.
Each option must include the risks for such an option, as this will assist in making a recommendation based on the project board’s risk appetite.
There is a temptation for the project manager to start creating detailed plans around some or all of the options, but this should be resisted as the project board may decide on different actions or consider options of their own.
In such a case, the effort to create plans will have been wasted. Keep the PRINCE2 Exception Report simple and precise!
If time is of the essence, the project manager may advise the board verbally that a PRINCE2 Exception Report is being created and inform them of the options currently being considered within the report.
They may be able to shed some light on their favoured approach or even instruct the project manager to plan a chosen option in more detail.
PRINCE2 Exception Report Recommendation.
This is the project manager’s recommended option, and it is essential to include why the other options were not considered and why this option is chosen.
Remember, the project board may decide not to take this recommendation, so a project manager would be wise to articulate clearly why this recommendation is being made.
The project initiation documentation is an essential source of information for the project manager in considering options and recommendations. The project plan and the various approach documents will be helpful in the creation of your PRINCE2 Exception Report.
Of particular assistance is the project product description containing the acceptance criteria and project objectives. The current stage plan will also be used as a source of reference.
The project manager is advised to have discussions with any or all appropriate stakeholders such as the senior user, senior supplier, project board executive, departmental or operational managers such as those responsible for finance, procurement, legal, and end-product operators, to ensure that their PRINCE2 Exception Report contains up-to-date and accurate information.
PRINCE2 Lessons Log.
This should capture any lessons that can be learned from this PRINCE2 Exception Report situation and consideration made whether such lessons can be applied for the remainder of this project and/or future projects.
Such as, lessons should be added to the lessons log. If the project board requests that the project manager create an exception plan to be reviewed at an exception assessment, then the end-stage report will include such lessons.
PRINCE2 Exception Report Summary.
The exception situation may have been caused by an external event that affected the project. Indeed, it may be the project board that brought this to the project manager’s attention. Other sources of information besides those mentioned above are the quality register, checkpoint reports, and highlight reports.
Pass Your PRINCE2 Exams with Projex Academy’s PRINCE2 Foundation and Practitioner Masterclass!
PRINCE2® 7 Foundation and Practitioner


Learn PRINCE2® 7 Foundation and Practitioner Online
** Enhance your PRINCE2 career now **
PRINCE2® Masterclass gives you the skills necessary to manage projects effectively and achieve your objectives.
Get 7 days a week 12 months one to one coaching with ex PRINCE2 examiner Dave Litten.
PRINCE2® is a globally recognized project management framework. By completing both the Foundation and Practitioner courses through our self-paced e-learning, you will develop an understanding of the methodology and learn how to effectively adapt it to any project.
The PRINCE2® 7 Foundation and Practitioner Masterclass is PeopleCert Accredited and guarantees to take you from PRINCE2 Novice to PRINCE2 Practitioner with our famous video learning, study guides and practice exams.
What Does the Masterclass Cover?
The PRINCE2 Foundation examination assesses your knowledge and comprehension of the PRINCE2 project management methodology as detailed in the syllabus. The PRINCE2 Practitioner examination, on the other hand, gauges your ability to apply and tailor the PRINCE2 method. Candidates who pass the Practitioner exam should be able to start implementing the method on an actual project with some guidance. However, their effectiveness may differ based on their experience in project management, the complexity of the project, and the level of support they receive in their work environment.