PRINCE2 Techniques for Risk Assessment 

 February 27, 2016

By  Dave Litten

Risk Assessment in PRINCE2 risk management

The Risk Management Approach document contains apart from other information, how risk assessment will be carried out, and more importantly the tools and approaches used for risk assessment.

Every project is different as too is the organization, culture and environment within which it takes place. What that means is that your risk assessment approach along with the scales used for the various tools and techniques will need to be chosen appropriately.

Estimating or Risk Assessment in a PRINCE2 project can be done in a variety of ways, and here are some of them:

Qualitative Risk Assessment.  This is just a fancy name for calculating the probability and impact for each risk. Then going on to rank the risks on that basis, and then typically actively managing the top 20% of the most severe risks while keeping a watchful eye on the remaining 80% of the rest.

Quantitative Risk Assessment. The main technique for this is the Probability impact grid.

The Probability impact grid. This grid contains ranking values that may be used to rank threats and opportunities qualitatively.

The probability scales are measures of probability derived from percentages, and the impact scales are selected to reflect the level of impact on project objectives during PRINCE2 risk assessment.

P-I Grid for risk assessment.

The values within the grid cells are the combination of a particular probability and impact, and the severity of the risk along with its risk assessment, can be determined by multiplying the probability by the impact.

A probability impact grid can be used to provide risk assessment of the severity of a risk and enable risks to be ranked so that management time and effort can be prioritized.

For example, the Project Board may set their risk tolerance at any risk with a value of greater than 0.2, and they may require a proactive response for any risk with a value of greater than 0.05

Pareto analysis This technique ranks or orders risks after risk assessment to determine the order in which they should be addressed. Pareto analysis can be used to focus management effort on those risks that have the potential to have the greatest impact on the project objectives.

Probability trees. These are graphical representations of possible events resulting from given circumstances. A probability tree can be used to predict an outcome in a qualitative way when historical data is used to populate the likelihood of each circumstance happening.

Probability trees assist in communicating to project participants or decision makers the likelihood of the different possible outcomes to a set of circumstances as part of risk assessment.

Expected value. This technique quantifies risk by combining the cost of the risk impact with the probability of the risk occurring. Expected value is useful when a tangible measure of risk is required to enable risks to be prioritized. For example, if the cost of a risk was £160,000 and its likelihood of occurrence was estimated at 25%, then the expected value would be £40,000

Identifying risks in risk assessment.

There are many ways of identifying possible risks prior to  risk assessment. It is important to come up with as many as possible, even if they are discounted later. Remember, any risk not identified may cause your project to fail! Here are some examples:

Risk prompt lists.  These are publicly available lists that categorize risks into types or areas and are normally relevant to a wide range of projects. Risk prompt lists are useful aids to help stimulate thinking about sources of risk in the widest context.

Brainstorming. This enables group thinking, which can be more productive than individual thinking. However, it is important to avoid criticism during the brainstorm as this can stop people contributing. In addition to identifying risks, brainstorming can also be used to understand the stakeholders’ views of the risks identified

Risk breakdown structure This is a hierarchical decomposition of the project environment assembled to illustrate potential sources of risk. Each descending level represents an increasingly detailed definition of sources of risk to the project.

The structure acts as a prompt and an aid to support the project management team in thinking through the potential sources of risk to the objectives.

Risk checklists. These are in-house lists of risks that have either been identified or have occurred on previous similar projects. Risk checklists are useful aids to ensure that risks identified on previous projects are not overlooked.

Review lessons. Risks are driven by uncertainty, so one of the most effective ways to reduce uncertainty is to review similar previous projects to see what threats and opportunities affected them.

There are numerous ways to break down risk and it may be useful to do more than one list.

For example, a risk breakdown structure could be broken down by PESTLE (political, economical, sociological, technological, legal/legislative, environmental), product breakdown structure, stage, benefits/objectives etc.

These structures will help to identify appropriate risk owners to develop responses.

There are many ways to carry out risk assessment, and here are some of the most often used techniques:

Risk models Take, for example, Monte Carlo analysis. This model enables simulation of ’what if’ scenarios using random numbers to determine whether each risk within a given range occurs or not.

The simulations are repeatedly run to predict the ’average’ level of risk to the project’s time or cost. The scenarios can also be used to model extreme cases (e.g. if nearly all the risks occur)

Expected monetary value This technique takes the expected values of a number of risks and sums them to arrive at an overall value. It provides a quick and easy risk assessment of a group of risks to understand their combined effect.

This course is DEPRECATED

The old PRINCE2 6th Edition Foundation and Practitioner syllabus was upgraded in 2024. Check out the brand NEW PRINCE2 7th Edition Masterclass, covering all the current syllabus, training material and online exam benefits HERE

5.0
Prince2 Practitioner Masterclass

Your Route To PRINCE2 6th Edition Practitioner

Study PRINCE2 6 Foundation and Practitioner Exams with our famous on-line course with streaming HD Video Lessons, study guides and mock exams. In the last fifteen years we have had 6,000+ Academy students successfully transform their careers as PRINCE2 Practitioners.

  • Bite Sized Lessons  The sheer size of PRINCE2 can be daunting. The Masterclass will guide you through the syllabus in easy to consume bite sized lessons
  • Be prepared and confident for the exams  Test your knowledge in a fun, entertaining environment with the PRINCE2 Foundation & practitioner exam revision tools
  • Enjoy yourself!  This PRINCE2 Foundation & Practitioner online course is broken into bite-size lessons, combining leading edge multimedia and interactive exercises for optimum enjoyment and knowledge retention
  • Feel confident with full tutorial support  Benefit from fast access to experienced, one-to-one learning support as you study via email and phone, so there is no need to feel isolated while you are learning
  • Take your time  Study at your own pace by bookmarking your progress and picking up where you left off at a speed that suits you

Dave Litten


Dave spent 25+ years as a senior project manager for UK and USA multinationals and has deep experience in project management. He now develops a wide range of Project Management Masterclasses, under the Projex Academy brand name. In addition, David runs project management training seminars across the world, and is a prolific writer on the many topics of project management.

Your Signature

{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}
Insert Content Template or Symbol

Join NOW!

Boost Your Career Now!

15% Discount on all courses with Coupon Code - PROJEX15