PRINCE2 Give ad hoc direction 

 July 14, 2017

By  Dave Litten

PRINCE2 Give ad hoc direction

Project board members may offer informal guidance or respond to requests for advice at any time during a project.

The need for consultation between the project manager and project board is likely to be the particularly frequent during the initiation stage and when approaching management stage boundaries.

Ad hoc direction may be given collectively or by individual project board members.

Give Ad Hoc Direction
adhoc1

There are a variety of circumstances that might prompt ad hoc direction, including:

  • Responding to requests, clarifying options, resolving conflict, etc
  • Responding to reports such as highlight report, exception report, issue report
  • Responding to external influences, for example changes in corporate priorities
  • Project board members individual concerns
  • Responding to changes in project board composition which may also require corporates, programme or customer approval

It is also possible that corporate, programme, or the customer revises the project mandate in response to events external to the project, or instructs the project board to close the project.

The project board has two primary options should the project mandate be changed in this way:

Treat it as a request for change, asking the project manager to replant the management stage and/or project

Stop, and restart the project by triggering premature closure.  This may result in additional costs compared with the request for change option.

The project board may appoint project assurance to undertake some other reviewing and assessing actions.  For example, inspecting a request for change to confirm that adequate impact assessment has been undertaken.

When making decisions, it is important to consider the impact on all stakeholders as laid down within the communications management approach.

PRINCE2 recommends the following Give ad hoc direction actions:

In response to informal requests for advice and guidance, seek advice from corporate, programme management or the customer if necessary.  Also ask the project manager to produce an issue report and/or an exception report.

In response to an escalated issue:

  • Seek advice from corporate, programme management or the customer is necessary
  • Make a decision within the project board’s delegated limits of authority

This decision could be regarding:

A problem or concern.  Ask for an exception plan or provide guidance

A request for change.  Approve, defer, reject or ask for more information.  Consider whether an exception plan is required

An off specification.  Grant a concession, defer, reject or ask for more information.  Consider whether an exception plan is required

In response to an exception report:

  • Seek advice from corporate, programme management or customer if necessary
  • Decide within the project boards delegated limits of authority, to:
  • Increase the tolerances that a forecast to be breached
  • Instruct the project manager to produce an exception plan, stating what will be acceptable
  • Instruct the project manager to close the project prematurely
  • Defer the exception for a fixed period.  This is a useful response if there is low confidence in the forecast that tolerances will be exceeded, or if the exception is contingent on a risk occurring.

In response to the receipt of a highlight report:

  • Review the highlight report to understand the status of the project
  • Ensure that the project remains focused on the corporate, programme management or customer objectives set, and remains justified in accordance with its business case
  • Ensure that the management stage is progressing according to plan

Keep corporate, programme management or the customer and other interested parties, informed about project progress, as defined within the communication management approach

Take actions as necessary, for example asking the project manager to produce an issue report and/or an exception report

In response to advice and decisions from corporate, programme management or the customer:

Ensure that the project management team is kept informed of external events that may affect it such as advising the project manager of a change of project board personnel

Notify the project manager of any changes in the corporates, programme management or customer environment that may impact on the project, and ensure appropriate action is taken.

This may involve:

  • Raising an issue to the project manager
  • Instructing the project manager to produce an exception plan
  • Instructing the project manager to close the project prematurely

Pass Your PRINCE2 Practitioner At First Try HERE!

Dave Litten


Dave spent 25+ years as a senior project manager for UK and USA multinationals and has deep experience in project management. He now develops a wide range of Project Management Masterclasses, under the Projex Academy brand name. In addition, David runs project management training seminars across the world, and is a prolific writer on the many topics of project management.

Your Signature

{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}
Insert Content Template or Symbol

Join NOW!

Boost Your Career Now!

15% Discount on all courses with Coupon Code - PROJEX15