July 2

0 comments

PRINCE2 7 Stage Boundary Management


The “Managing a Stage Boundary” process involves reporting on stage performance and planning the next stage, but missteps can lead to poor project board decisions.

In PRINCE2, the “Managing a Stage Boundary” process when executed effectively, empowers the project board to make confident go/no-go decisions. When handled poorly, it can send an otherwise promising project down the wrong track.

managing a stage boundary

Why Stage Boundary Management Matters

Each stage in PRINCE2 is a self-contained unit of control. Managing the transition from one to the next ensures that:

  • Progress is measured objectively.
  • Risks and lessons are addressed.
  • Plans remain aligned with business needs.

Key Activities in Managing a Stage Boundary

To help the project board make informed decisions, the following tasks are critical:

  • Produce the End Stage Report: Summarize stage achievements, issues encountered, and status against tolerances (time, cost, scope, quality).
  • Update the Business Case & Risk Register: Reflect updated costs, forecast benefits, and revised risk exposure.
  • Revise the Project Plan & Next Stage Plan: Incorporate lessons learned and adjust resource allocations or timelines accordingly.
  • Prepare Exception Plans (if needed): If tolerances were breached, justify how corrective actions will return the project to alignment.
  • Seek Approval: Present the next stage plan and request authorization to proceed.

Managing a Stage Boundary Purpose

The purpose of the process of managing a stage boundary is to enable the project manager to provide the project board with sufficient information to be able to:

  • review the success of the current stage
  • prepare the next stage plan
  • review the updated project plan
  • confirm continued business justification and acceptability of the risks.

Therefore, this process should be executed at, or close to, the end of each stage.

Projects do not always go to plan, and in response to an exception report (if the stage or project is forecast to exceed its tolerances), the project board may request that the current stage and possibly the project is replanned.

The output from replanning is an exception plan that is submitted for the project board’s approval in the same way that a stage plan is submitted for approval. Exceptions are another possible trigger for this process.

Managing a Stage Boundary Objectives

These are to:

  • assure the project board that all products in the current stage plan have been completed and approved
  • prepare a stage plan or exception plan for the next stage review and if necessary, update the project initiation documentation, in particular the business case, project plan, user’s quality expectations, management approaches, project management team structure, and role descriptions
  • provide the information needed for the project board to assess the continuing viability of the project
  • record any information or lessons that can help later stages of this project or other projects
  • request authorization to start the next stage.


For exceptions, the objectives of the process of managing a stage boundary are similar to those listed above but include preparing an exception plan and seeking approval to replace the project or current stage plan with the exception plan.

Managing a Stage Boundary Context

The process of managing a stage boundary is based on dividing the project into stages.

A project, whether large or small, must ensure that the products it creates will deliver the benefits sought, either in their own right or as part of a programme or portfolio.

The business justification of the project should be reconfirmed at the end of each stage. If necessary, the project can be redirected or stopped to avoid wasting time and money.

It is important to recognize that projects can go wrong or be affected by external factors that invalidate the business justification.

An early identifier of potential failure is the project manager’s forecast that any of the project or stage tolerances are likely to be exceeded.

In such cases, it is important to have a mechanism for corrective action to bring the project back in the right direction and under control.

A positive decision not to proceed is not failure. However, providing insufficient information that prevents the project board from making an informed decision is a failure, as it may lead to a wrong decision or an unnecessarily delayed decision.

The process of managing a stage boundary provides a means by which an exception procedure can be implemented.

PRINCE2 End Stage Report Template

Executive Summary
Brief overview of the stage objectives and overall delivery status. Notable achievements or issues that impacted outcomes.
Stage Performance Overview
Time: Planned vs. actual duration with reasons for variance.
Cost: Stage budget vs. actual spend; explanation of any deviations.
Scope & Quality: Deliverables completed; quality criteria met or missed.
Product Status

Inventory of products delivered in the stage.
Product Descriptions updates and quality review summaries.
Issues and Changes
Summary of key issues encountered and how they were managed.
Approved change requests and their impacts.

Risk Management

Overview of current risks and mitigation progress.
New risks identified and recommended actions.

Lessons Learned

What worked well and should be replicated.
Challenges to avoid in future stages.
Contributions from team retrospectives.

Business Case Update

Revised cost-benefit analysis.
Any shifts in assumptions or external factors.
Next Stage Plan
High-level breakdown of next stage activities and timeline.
Resource needs, team updates, dependencies.

Recommendations

Whether to proceed, revise, or halt the project.
Requests for further guidance or decisions from the project board.

Click here to find out more

PRINCE2® 7 Foundation and Practitioner

5.0
PRINCE2 Practitioner Masterclass
PRINCE2 axelos peoplecert trademark copyright

Learn PRINCE2® 7 Foundation and Practitioner Online

** Enhance your PRINCE2 career now **

PRINCE2® Masterclass gives you the skills necessary to manage projects effectively and achieve your objectives.

  • Optional:   Official Online Exam
  • Course type: E-learning
  • Duration: Approx 45 hours
  • Delivery: Online

Get 7 days a week 12 months one to one coaching with ex PRINCE2 examiner Dave Litten.

PRINCE2® is a globally recognized project management framework. By completing both the Foundation and Practitioner courses through our self-paced e-learning, you will develop an understanding of the methodology and learn how to effectively adapt it to any project.

The PRINCE2® 7 Foundation and Practitioner Masterclass is PeopleCert Accredited and guarantees to take you from PRINCE2 Novice to PRINCE2 Practitioner with our famous video learning, study guides and practice exams.

  • Overview

  • Objectives

  • Exam information

  • Duration

What Does the Masterclass Cover?

The PRINCE2 Foundation examination assesses your knowledge and comprehension of the PRINCE2 project management methodology as detailed in the syllabus. The PRINCE2 Practitioner examination, on the other hand, gauges your ability to apply and tailor the PRINCE2 method. Candidates who pass the Practitioner exam should be able to start implementing the method on an actual project with some guidance. However, their effectiveness may differ based on their experience in project management, the complexity of the project, and the level of support they receive in their work environment.

  • Prepare for your PRINCE2 7 Foundation and PRINCE2 7 Practitioner Exams with our famous on-line course with streaming HD Video Lessons, PDF study guides and Mock Eams. 
  • We are a PEOPLECERT (AXELOS) Business Partner – Our PRINCE2 Masterclass is fully certified for PRINCE2 7th Edition Foundation and Practitioner.
  • Bite Sized Lessons  The sheer size of PRINCE2 can be daunting. The Masterclass will guide you through the syllabus in easy to consume bite sized lessons
  • Enjoy yourself!  This PRINCE2 Foundation & Practitioner online course is broken into bite-size lessons, combining leading edge multimedia and interactive exercises for optimum enjoyment and knowledge retention
  • Take your time  Study at your own pace by bookmarking your progress and picking up where you left off at a speed that suits you
  • Be prepared and confident for the exams  Test your knowledge in a fun, entertaining environment with the PRINCE2 Foundation & practitioner exam revision tools
  • In the last 20+ years we have had 9,000+ Academy students successfully transform their careers as PRINCE2 Practitioners.

Tags

PRINCE2 7 Stage Boundary Management


You may also like

The 80/20 rule (also known as the Pareto Principle) within Lean Six Sigma methodologies
{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}

Direct Your Visitors to a Clear Action at the Bottom of the Page