Project Management actions
The project manager must provide the project board with summary information about the status of
the stage and project and distribute other information to the stakeholders at a frequency
documented in the communication management approach, as defined by the project board.
Recommended actions for the project manager:
- assemble the information from the checkpoint reports, project log, and any significant revisions to the stage plan for the current reporting period (the information is gained from the review of the stage status).
- assemble a list of corrective actions (as noted or recorded in the project log) undertaken during the reporting period; this will assure the project board that the project manager is acting within the agreed tolerances (the information is gained from taking corrective action
- review the highlight report for the previous reporting period.
- produce the highlight report for the current reporting period.
- distribute the highlight report
For projects using an iterative-incremental delivery method such as agile, the highlight report may be based on a ‘pull’ system, whereby the project board looks at progress charts being maintained by the project manager and development teams.
Highlight Report structure
The purpose of a highlight report is to provide the project board (and possibly other stakeholders)
with a summary of the stage status at intervals defined by them.
Executive summary: project manager’s report
Period: the reporting period covered by the highlight report
Follow-ups: the outstanding items from previous reports (for example, action items completed or unresolved)
This reporting period: the actual progress of work packages, including those pending authorization, in
execution, and completed in the period (if any work packages are being performed by external suppliers,
this information may be accompanied by purchase order and invoicing data); products completed in
the period; products planned but not started or completed in the period (providing an early warning
indicator or potential breach of time tolerance); any corrective actions taken during the period
Next reporting period forecast: progress of work packages, including those to be authorized, in
execution and to be completed during the next period (if the work packages are being performed
by external suppliers, this information may be accompanied by purchase order and invoicing data);
products to be completed in the next period; corrective actions to be completed during the next period
Stage and project tolerance status: how execution of the project and stage are performing against
their tolerances (for example, cost/time actuals and forecast)
Key issues and risks: a summary of the actual or potential issues and risks (including a list of
requests for change or off-specifications raised, actioned, or pending for the period)
Lessons (if appropriate): a review of what went well, what went badly, and any recommendations for
consideration by the business; sourced from the lessons log or any lessons reports that may exist.
PRINCE2® 7 Foundation and Practitioner


Learn PRINCE2® 7 Foundation and Practitioner Online
** Enhance your PRINCE2 career now **
PRINCE2® Masterclass gives you the skills necessary to manage projects effectively and achieve your objectives.
Get 7 days a week 12 months one to one coaching with ex PRINCE2 examiner Dave Litten.
PRINCE2® is a globally recognized project management framework. By completing both the Foundation and Practitioner courses through our self-paced e-learning, you will develop an understanding of the methodology and learn how to effectively adapt it to any project.
The PRINCE2® 7 Foundation and Practitioner Masterclass is PeopleCert Accredited and guarantees to take you from PRINCE2 Novice to PRINCE2 Practitioner with our famous video learning, study guides and practice exams.
What Does the Masterclass Cover?
The PRINCE2 Foundation examination assesses your knowledge and comprehension of the PRINCE2 project management methodology as detailed in the syllabus. The PRINCE2 Practitioner examination, on the other hand, gauges your ability to apply and tailor the PRINCE2 method. Candidates who pass the Practitioner exam should be able to start implementing the method on an actual project with some guidance. However, their effectiveness may differ based on their experience in project management, the complexity of the project, and the level of support they receive in their work environment.