PRINCE2 - Managing PRINCE2 Issues and Risks
There are various strands of the PRINCE2 Method that can cause overwhelm for those preparing for their PRINCE2 Practitioner Exam.
One of these areas is the treatment of issues and risks. There are two chapters dealing with these within the official PRINCE2 Manual - the Risk Theme and the Change Theme.
The latter, because PRINCE2 treats problems, concerns, requests for change, and off-specification as all types of issue.
Each of the above chapters lays out the steps and sequence for dealing with issues (in addition to changes) and risks
The problem occurs when thinking about where exactly are these dealt with. The answer is in the Controlling a Stage process.
In this article, I will deal with the main THREE activities within Controlling a Stage:
These three activities should be seen as a logical sequence.
Capture and examine issues and risks
In the course of managing the project, various issues will occur and risks may be identified.
They will arrive in an ad hoc manner and will need to be captured in a consistent and reliable way.
Any member of corporate, programme management or the customer, the project or other stakeholders may raise an issue or risk.
Before making a decision on a course of action , each issue or risk should be registered and then assessed for its impact.

Here are the actions that you will want to take:
Responsibilities

Escalate issues and risks
A management stage should not exceed the tolerances agreed with the project board.
The project manager can only take corrective action or maintain the status quo as long as the management stage (or project) is forecast to be completed within the tolerances set by the project board
This activity applies where any corrective action within the project manager's control would not save the management stage (or project) from going beyond the
tolerances agreed.
This applies to all types of issue and risk (or aggregations of them) that cannot be resolved within the tolerances set by the project board
As it may take some time to gather the information to create an exception report, it is recommended that the project board be alerted as early as possible.
Therefore, the project manager may wish to execute this activity in two steps:
1. an early notification to the project board of the forecast exception situation so that the board is prepared
2. followed by supporting information in the form of an exception report

The project manager should execute any decision by the project board in response to the escalation.
Escalating issues and risks is good practice and should not be seen as failure. The earlier that issues are escalated, the more time is available to implement any corrective actions
Responsibilities

You will want to carry out the following actions:
Take corrective action
Changes and adjustments to the project need to be made in a considered and rational way, even when they appear to be easily manageable and within tolerances.
In taking corrective action, the objective is to select and, within the limits of the management stage and project tolerances, implement actions that will resolve deviations from the plan.
Corrective action is triggered during the review of the management stage status and typically involves dealing with advice and guidance received from the project board, and with issues raised by team managers

You will want to take the following actions:
Responsibilities

PRINCE2 Roadmap Video
As a PRINCE2 Coach, Trainer (and ex-examiner!), I have developed an amazing PRINCE2 Roadmap, 30-minute video that will jet-power your PRINCE2 process knowledge.
It will open your eyes to exactly how PRINCE2 works.
The PRINCE2 official manual will now make much easier reading!
You are now on your way to become a PRINCE2 Practitioner!
Here at Projex Academy we have a rich set of professional project management-related training video courses.
PRINCE2 Training
PRINCE2 Foundation and Practitioner Masterclass
Here is our PRINCE2 Foundation and Practitioner Masterclass