MS Project – What If I Don’t Know How Long a Task Will Take To Complete? 

 August 2, 2020

By  Nick Litten

What If I Don’t Know How Long a Task Will Take To Complete?

Do I Have to Enter a duration?

If a task is Manually Scheduled, you can enter To Be Decided (tbd), or similar text into the duration field.  If you also enter a Start Date or you attempt to link a Manually Scheduled task that has no duration, Project gives you a Start-Only Placeholder Gantt bar.

Nick Litten


Dave Litten