Why Do I Get Light Blue Task Bars?

In Project 2010, for manually scheduled tasks that have a duration but no Start or Finish dates, you get a Placeholder Gantt bar that has a faded, light blue appearance.

Dave Litten


Dave spent 25+ years as a senior project manager for UK and USA multinationals and has deep experience in project management. He now develops a wide range of Project Management Masterclasses, under the Projex Academy brand name. In addition, David runs project management training seminars across the world, and is a prolific writer on the many topics of project management.