FAQ MS Project – How Do I Automatically Update Task Dates in Project 2010? 

 August 2, 2020

By  Dave Litten

How Do I Automatically Update Task Dates in Project 2010?

In Manual Scheduling, Project does not automatically reschedule tasks when you edit predecessor information.

If you want Project 2010 to do this, you must change the task mode to Auto Scheduled by using the drop down in the Task Mode column.  Alternatively, you can click on the Respect Links icon on the Task tab.  This reschedules the task but keeps it manually scheduled.

Dave Litten


Dave spent 25+ years as a senior project manager for UK and USA multinationals and has deep experience in project management. He now develops a wide range of Project Management Masterclasses, under the Projex Academy brand name. In addition, David runs project management training seminars across the world, and is a prolific writer on the many topics of project management.

The Projex Academy

related posts:

{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}

Project Management Masterclasses