How Do I Automatically Update Task Dates in Project 2010?
In Manual Scheduling, Project does not automatically reschedule tasks when you edit predecessor information.
If you want Project 2010 to do this, you must change the task mode to Auto Scheduled by using the drop down in the Task Mode column. Alternatively, you can click on the Respect Links icon on the Task tab. This reschedules the task but keeps it manually scheduled.