End Stage Report – the steps to its creation
The PRINCE2 process Managing a Stage Boundary is used to either prepare for an end stage assessment, or for an exception assessment. For the purpose of this article, by shall only concentrate all the former.
The purpose of an end stage assessment it is to provide the project board with sufficient information to make an informed choice about whether to proceed with the project or not.
Before discussing the content of an end stage report, is therefore important to understand the sources of information that will be included within it. It makes sense therefore, to first look at the activities within the Managing a Stage Boundary process itself.
Managing a Stage Boundary
The following diagram shows the typical route:

End Stage Report
When the project manager sees the current stage nearing completion, it will trigger him to refer to the Managing a Stage Boundary process as above. The first step this to create the next stage plan which will be drawn from the top level details within the project plan.


The Stage Plan
Using the PRINCE2 technique of product based planning, these top-level details will be decomposed into a detailed level suitable for day to day management within the next stage.
The project manager will want to involve as many appropriate and relevant people as possible to ensure a robust and achievable stage plan is created. In particular specialists team members, senior suppliers, and project assurance should be involved in creating the next stage plan.
The project initiation documentation should be referenced, in particular, for the relevant standard documents, since risk, quality, configuration management, and communication aspects of the project will heavily influence the next stage plan.
As part of Product-Based planning, new products will be identified. These may consist of further refined existing products or entirely new products. Whichever the case may be, new product descriptions will need to be created along with their relevant quality criteria. For the quality register will need to be updated with the relevant information for carrying out quality checks within the next stage.
Also, configuration item records will need to be created or modified for each new product in order to track the status of that product.
As part of carrying out planning for the next stage, new or modified risks may be identified, and these too will need to be entered into the risk register and their appropriate response actions included within the next stage plan. In a similar way any on-going issues and their actions may need to be included within the plan (unless they are currently being dealt with).
As a consequence of creating the more detailed next stage plan, it is highly likely that the project plan will need to be updated and refined. There are several reasons for this:
- The newly created next stage plan will normally have a different stage end date, a different cost, different products and different resources to those originally estimated within the project plan.
- Since the current stage is now coming to close, actual information such as products, cost and end dates will now need to be entered into the updated project plan.
- The business environment may have changed since the project initiation document was signed off. For example, the user group may have different objectives, or market forces may have changed.
Once the project plan has been updated, the business case also needs to be updated to ensure that the project is still providing continued business justification. For example project or operational costs may rise, schedules may be delayed, or new competitors may have arrived and hence the end-product may need to be modified or enhanced.
Typically, the project manager and the project board executive will review sections of the business case and update them necessary.
In a similar way to above the project manager and executive should review the organization’s risk appetite and the overall risk situation to ensure that it remains within risk tolerances.
They should also review the benefits management approach to ensure there has been updated that the results of any benefit reviews that may have taken place, and that such results should be compared with the expected results. Similarly any planned benefit reviews are included in the stage plan and the project plan.
All of the above culminate in the creation of the End Stage Report as shown in this activity:
End Stage Report
In the report stage end activity, the end stage report will be created which will be review by the project board along with the other outputs of the managing a stage boundary process in order to decide whether to proceed to the next stage of the project or not.
The project manager may wish to create a lessons report, particularly if certain lessons should be applied to the remainder of this project or would be useful to other projects at this point in time. It might be useful to remind you of the content and structure of a lessons report:
PRINCE2® 7 Foundation and Practitioner


Learn PRINCE2® 7 Foundation and Practitioner Online
** Enhance your PRINCE2 career now **
PRINCE2® Masterclass gives you the skills necessary to manage projects effectively and achieve your objectives.
Get 7 days a week 12 months one to one coaching with ex PRINCE2 examiner Dave Litten.
PRINCE2® is a globally recognized project management framework. By completing both the Foundation and Practitioner courses through our self-paced e-learning, you will develop an understanding of the methodology and learn how to effectively adapt it to any project.
The PRINCE2® 7 Foundation and Practitioner Masterclass is PeopleCert Accredited and guarantees to take you from PRINCE2 Novice to PRINCE2 Practitioner with our famous video learning, study guides and practice exams.
What Does the Masterclass Cover?
The PRINCE2 Foundation examination assesses your knowledge and comprehension of the PRINCE2 project management methodology as detailed in the syllabus. The PRINCE2 Practitioner examination, on the other hand, gauges your ability to apply and tailor the PRINCE2 method. Candidates who pass the Practitioner exam should be able to start implementing the method on an actual project with some guidance. However, their effectiveness may differ based on their experience in project management, the complexity of the project, and the level of support they receive in their work environment.