Controlling The PRINCE2 Work Package
the creation of products and work package control
Brought to You by Dave Litten
THE PURPOSE AND USE OF THE WORK PACKAGE
Within the Controlling a Stage process, it is vital that any work to create the specialist products must not start unless the work package has been authorized by the project manager, for if the team made their own decisions about when and what work should start, then chaos would ensue.
Therefore, work packages are used to define and control work that needs to be done and to optionally set tolerances or the team manager.
The work package is used to pass responsibility for the work to be carried out to the team manager or the team members themselves, and are used within the Managing Product Delivery process
A work package can be done informally or formally dependent upon the nature of the project, and it should include the work to create one or more specialist products. Such a work package may include sections from, or reference to, the project plan, stage plan or project initiation documentation.
For example, the stage plan should be examined to understand what products are to be produced, and cost and work effort that the work package will contain, and any tolerances that are available.
The project initiation documentation should also be exam and to note the project controls required with regard to progress reporting arrangements, the quality standards that must be met, and these are defined within the quality management approach, and if any products are to be handed over after approval during the stage. The change management approach will lay out any handover procedures.
The project manager is responsible for the activity of authorize a work package, and this will be the first activity within a stage. Work packages may be given out singularly or several at a time, and every work package must contain at least one product description.
The team manager will optionally produce a team plan, and this will cover the execution of one or more work packages.
Whenever the project manager takes corrective action normally in response to an issue or risk, then this may result in the issue of a new, or a modified work package.
Each work package must be reviewed with the team manager to ensure that they have accepted it and that they are authorize to begin work. If a team managers team plan has been created then they should be reviewed by the project manager, or at least the milestone extract from it if the team plan contents should not be seen by the project manager.
As a result of accepting a work package, it may be necessary to update the stage plan, the configuration item records to show the status of the work package products are now under creation, the plans quality management activities should be updated with in the quality register, and if required the risk and issue registers should also be updated as laid out within the risk management approach and the change management approach.
Of particular importance is the project assurance should be consulted to ensure that the selected quality reviewers are acceptable to both from a knowledge, skills and experience perspective and that they are suitably independent from those who are to create the products.
The team manager will produce checkpoint reports at the frequency and formality laid down within each work package. The project manager will use these to ensure that the work package and hence the stage, is on track to deliver on time, budget, and within tolerance.
For a work package to be deemed complete, all of the work should have been carried out, the quality register entries show the products are complete, have passed their quality checked and have been approved as laid out within the work package. The project manager should also confirm that the configuration item record for each product within the work package has been updated.
The typical contents of a work package:
Controlling PRINCE2 Work Packages
This will take you beyond the standard information that is available within the PRINCE2 official Manual, and to give you a feel of the real dynamics that occur within a typical PRINCE2 stage using the Controlling a Stage process.
In the PRINCE2 processes ‘controlling a stage’ and ‘managing product delivery’ there is a partnership between the project manager and the team manager or the team members themselves. This partnership comes about as result of the project manager being responsible for managing the entire stage, while the team manager is responsible for ensuring that the work package is carried out.
But it goes further than that; you see what is happening here is that the team manager and the specialist team do not have the authority to carry out any work unless the project manager authorizes it via a work package. Within the scope of the stage, the team are not allowed to carry out any work on any potential work packages unless they too are authorized by the project manager.
This may seem rather autocratic, but it is a powerful control as many times the reason why the budget is overspent is because the specialist team are doing what they think should be done rather than what they have been told to do!
Work Package Control
As an absolute minimum, the project manager may give out one work package whose scope covers the creation of all of the products within that stage. But normally this is not the case as there is usually a logical sequence within which the work and product creation must adhere to.
So it is highly likely that several work packages will be authorized by the project manager in either a parallel or series fashion. Suppose for example that the project manager has several teams are working within a particular stage, it is highly likely that the project manager will want to specify the exact work and products to be created by each team, and will therefore issue more than one work package at the same point in time.
Remember also, that the project may be using a third party, and they too may receive a series of parallel and/or series set of work packages (maybe at the same time that ‘internal’ work packages are given to the organisation’s own resources.
Checkpoint Report
It is the team manager’s responsibility not just to except each work package but also to agree that the products within it can be created within, for example, cost and time constraints. But a work package contains other instructions such as creating a regular checkpoint report back to the project manager.
The checkpoint report may be a document, an e-mail, a phone call, or a face to face meeting. Such details are laid down within the work package itself.
This means of course, that the project manager will receive many checkpoint reports at any one time and throughout the remainder of the stage time-frame.
It is worth reminding ourselves that PRINCE2 advises that the team manager or the specialist team be involved in planning their responsibilities for the coming next stage.
This would occur when planning the next stage plan before that stage plan has been approved by the project board. The point here is that when the project manager gives out work packages and asks the team manager to approve it, it is unlikely that there will be any new surprises or disagreements.
Rather, when the project manager issues and authorizes the work package, it is seen as an opportunity for the project manager and the team manager to run through the details one more time to make sure they are clear and acceptable
Team Plan For Work Packages
On some occasions, the team manager may wish to create a team plan that covers one or more work packages that they are responsible for. In which case, this team plan will need to be created by for the team manager can agree to accept the work package.
The reasons for this are that the team manager will develop some form of a Gantt chart, and check that the schedule is realistic and it is feasible based on resource availability. Again, it is likely that the team plan had been already created during the planning of that particular stage as mentioned above.
But care should be taken here, as any planning and discussions of work to be done on the next stage will likely take time and cost, and the wise project manager will ensure that such costs are available within the current stage or the next stage plans.
PRINCE2 also advises that project support will need to create new configuration item records for the products are about to be produced.
Work Package Progress
The project manager will be using the checkpoint reports as one of the main inputs to creating the regular highlight report that was agreed with the project board at stage approval time. The checkpoint reports will contain the information, structure and format as laid down within the work package.
The project manager will want to collect actual information such as work effort, cost, and the duration of the work activities. If this is being done via time sheets, then it is likely that project support a will aggregate and report such information to the project manager.
The project manager will also want to know that the products are fully complete and that they are being produced to the right level of quality. The project manager will want to check that the right tests are being done at the right time by the right people. In addition, the project manager will readily check the contents of the quality register which describes what actions have been taken and what the true status of each product is.
Put simply, each product is first created, then tested, then checked that it meets the quality criteria, and if it passes, that the right individual has authorized the product as complete.
Work Package Completion
When all of the products within a work package are deemed complete as explained above, the team manager will deliver those products to the project manager as part of the process activity ‘deliver a work package’.
Of course, in the real world, that may not happen exactly as described above. It may be that the team manager merely a advises the project manager that the products are complete and that the actual products themselves are passed to someone else.
So who is this "someone else"?
Well, it may be the customer, the end user, a secure storage area, configuration management, or a named individual. But what if the product is an installed set of wiring for example at a customer’s site? In such a case, after acceptance has been performed and agreed, the team manager will inform the project manager that the product has been ‘delivered’.
All of the above points, demonstrate the control power that using the PRINCE2 methodology provides to a project and the organization.
You see, it is only when each product has been accepted by the person authorized to do so, that the product is truly 100% complete. In this way, the frailty of human progress interpretation is neatly sidestepped.
By including the date that each product is fully complete as a milestone within stage and team plans, then true and unambiguous progress status can be used. Knowing exactly where you are, gives far more power to providing forecast data and hence considerably improves control aspects of the project.