PRINCE2 7 Terminology checklist – part 2 

 August 27, 2024

By  Dave Litten

PRINCE2 7 Terminology checklist – part 2

corrective action

A set of actions to resolve a threat to a plan’s tolerances or a defect in a product.

cost tolerance

The permissible deviation in a plan’s cost that is allowed before it needs to be escalated to the next level of management. See also tolerance.

Culture

The set of shared attitudes, values, goals, and ways of working that characterize a group of people.

Customer

The person or group from the business who commissioned the work and will benefit from the end results. The term ‘customer’ is only used where there is a commercial relationship between the business and the supplier.

daily log

A log used to record problems/concerns that can be handled by the project manager informally.

Dashboard

A way of representing vast amounts of decision-support data that gives a current summary, usually in graphic, easy-to-read form, of key information relating to progress and performance.

data analytics

The means of using and analysing data to support effective decision-making or to bring efficiency through the automation of tasks.

Deliverable

See output.

delivery method

The way in which the work of the project is to be delivered. The project may rely on one or more delivery methods to create the required products. Typical delivery methods include iterative-incremental, linear-sequential, or hybrid.

delivery model

The organizational and commercial arrangements to be deployed to meet the project objectives given the project constraints and capabilities of the user, business, and supplier organizations. It is described in the commercial management approach and reflected in the project management team structure.

Dependency

A dependency means that one product is dependent on another. There are at least two types of dependency relevant to a project, internal and external.

DevOps

An organizational culture that aims to improve the flow of value to customers. DevOps focuses on culture, automation, Lean, measurement, and sharing (CALMS).

dis-benefit

The measurable decline resulting from an outcome perceived as negative by the investing organization and which detracts from one or more business objectives.

early warning indicators

Describe indicators to be used to track critical aspects of the project so that if certain predefined levels are reached, corrective action will be triggered. They will be selected for their relevance to the project objectives.

end project report

A report given by the project manager to the project board, confirming the handover of all products. It includes a review of the performance of the project, any subsequent recommendations, and request approval to close the project.

end stage report

A report given by the project manager to the project board at the end of each stage. This provides information about the project’s performance during the stage and the project status at the stage end.

event-driven control

A control that takes place when a specific event occurs. This could be, for example, the end of a stage, the completion of the project initiation documentation, or the creation of an exception report. It could also include organizational events that may affect the project, such as the setting of annual budgets.

Exception

A situation where it can be forecast that there will be a deviation beyond the tolerance levels agreed between the project manager and the project board (or between the project board and business layer).

exception plan

A plan that follows an exception report and explains how the project will respond to the exception within the stage.

exception report

A report from the project manager to the project board to explain where tolerances have or are forecast to be breached for the stage or project and to request direction from the project board.

external dependency

An external dependency is one between a project product and a product or activity outside the scope of the project. In these circumstances, the project team does not have complete control over the dependency.

external products

Are products developed or provided outside of the project’s control but which the project is dependent on, for example, the publication of a new standard.

follow-on action recommendations

Actions to be taken by the business following the phased handover of any products during the stage.

Forecast

A prediction made by studying historical data and past patterns.

Governing

The ongoing activity of maintaining a sound system of internal control by which the directors and officers of an organization ensure that effective management systems, including financial monitoring and control systems, have been established to protect assets, earning capacity, and the reputation of the organization.

Handover

The transfer of ownership of a set of products to the respective user(s). The set of products is known as a release. There may be more than one handover in the life of a project (phased delivery). Confirmation of the final handover takes place in the ‘closing a project’ process.

highlight report

A time-driven report from the project manager to the project board on stage progress.

initiation stage

The period from when the project board authorizes initiation to when it authorizes the project (or decides not to proceed with it). The detailed planning and establishment of the project management infrastructure is covered by the ‘initiating a project’ process.

internal dependency

An internal dependency is one between two products of a project. In these circumstances, the project team has control over the dependency.

Issue

An event relevant to the project that requires project management consideration.

issue register

A register used to capture and maintain information on all of the issues that are being managed formally. The issue register should be monitored by the project manager on a regular basis.

issue report

A report containing the description, impact assessment, and recommendations for a response to an issue. It is created only for those issues that need to be handled formally.

Go to Part THREE here

PRINCE2® 7 Foundation and Practitioner

5.0
Prince2 Practitioner Masterclass
Prince2 Axelos Peoplecert Trademark Copyright

Learn PRINCE2® 7 Foundation and Practitioner Online

** Enhance your PRINCE2 career now **

PRINCE2® Masterclass gives you the skills necessary to manage projects effectively and achieve your objectives.

  • Optional:   Official Online Exam
  • Course type: E-learning
  • Duration: Approx 45 hours
  • Delivery: Online

Get 7 days a week 12 months one to one coaching with ex PRINCE2 examiner Dave Litten.

PRINCE2® is a globally recognized project management framework. By completing both the Foundation and Practitioner courses through our self-paced e-learning, you will develop an understanding of the methodology and learn how to effectively adapt it to any project.

The PRINCE2® 7 Foundation and Practitioner Masterclass is PeopleCert Accredited and guarantees to take you from PRINCE2 Novice to PRINCE2 Practitioner with our famous video learning, study guides and practice exams.

  • Overview

  • Objectives

  • Exam information

  • Duration

What Does the Masterclass Cover?

The PRINCE2 Foundation examination assesses your knowledge and comprehension of the PRINCE2 project management methodology as detailed in the syllabus. The PRINCE2 Practitioner examination, on the other hand, gauges your ability to apply and tailor the PRINCE2 method. Candidates who pass the Practitioner exam should be able to start implementing the method on an actual project with some guidance. However, their effectiveness may differ based on their experience in project management, the complexity of the project, and the level of support they receive in their work environment.

  • Prepare for your PRINCE2 7 Foundation and PRINCE2 7 Practitioner Exams with our famous on-line course with streaming HD Video Lessons, PDF study guides and Mock Eams. 
  • We are a PEOPLECERT (AXELOS) Business Partner – Our PRINCE2 Masterclass is fully certified for PRINCE2 7th Edition Foundation and Practitioner.
  • Bite Sized Lessons  The sheer size of PRINCE2 can be daunting. The Masterclass will guide you through the syllabus in easy to consume bite sized lessons
  • Enjoy yourself!  This PRINCE2 Foundation & Practitioner online course is broken into bite-size lessons, combining leading edge multimedia and interactive exercises for optimum enjoyment and knowledge retention
  • Take your time  Study at your own pace by bookmarking your progress and picking up where you left off at a speed that suits you
  • Be prepared and confident for the exams  Test your knowledge in a fun, entertaining environment with the PRINCE2 Foundation & practitioner exam revision tools
  • In the last 20+ years we have had 9,000+ Academy students successfully transform their careers as PRINCE2 Practitioners.

Dave Litten


Dave spent 25+ years as a senior project manager for UK and USA multinationals and has deep experience in project management. He now develops a wide range of Project Management Masterclasses, under the Projex Academy brand name. In addition, David runs project management training seminars across the world, and is a prolific writer on the many topics of project management.

Your Signature

{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}
Insert Content Template or Symbol

Join NOW!

Boost Your Career Now!

15% Discount on all courses with Coupon Code - PROJEX15