PRINCE2 7 Tolerances in planning
Various constraints, such as schedules and resources, drive many projects. For example, a project that must be completed by a specific date would be considered a schedule-driven project.
On the other hand, a project that must be delivered with resources beyond those authorized in the project initiation documentation would be considered a resource-driven project.
A crucial element of effective planning is understanding which constraints take precedence, selecting which approaches to use and the appropriate tolerances for control.
PRINCE2 includes tolerances for various project constraints, such as benefits, time, cost, quality, scope, risks, and sustainability. Each of these tolerances is set to manage the constraints within acceptable limits, ensuring the project remains on track and delivers the desired outcomes.
The PRINCE2 technique for planning is a collaborative process that involves the project management team in setting tolerances. This approach balances the need for the project board to maintain effective control while enabling the project manager or team manager to achieve efficient delivery, fostering a sense of shared responsibility.
PRINCE2 time tolerance in planning
The permissible deviation in a plan’s time that is allowed before the deviation needs to be escalated to the next management level. If this tolerance is exceeded, it could indicate a potential risk to the project’s timeline and require higher-level intervention to promptly address the issue.
For instance, in a schedule-driven project, the plan’s time tolerance is often narrow, possibly set to zero. This indicates that delays would significantly jeopardize the project’s success, underscoring the importance of timely execution and making the audience aware of the potential risks.
PRINCE2 cost tolerance in planning
A plan’s cost deviation is permissible before it needs to be escalated to the next management level.
The plan for a project that must be delivered within a fixed budget will have a narrow cost tolerance, possibly set to zero, indicating that there is no room for an increase in cost.
PRINCE2 scope tolerance in planning
The permissible deviation in a plan’s scope is allowed before it needs to be escalated to the next management level.
The plan for a project delivering a new product to an organization might specify some tolerance level for initial support and user training after acceptance. This is to ensure a smooth transition to the new business as usual.
How wide or narrow each tolerance is set for each level of plan improves the understanding of which constraints take precedence and how they should be incorporated into a plan.
PRINCE2® 7 Foundation and Practitioner


Learn PRINCE2® 7 Foundation and Practitioner Online
** Enhance your PRINCE2 career now **
PRINCE2® Masterclass gives you the skills necessary to manage projects effectively and achieve your objectives.
Get 7 days a week 12 months one to one coaching with ex PRINCE2 examiner Dave Litten.
PRINCE2® is a globally recognized project management framework. By completing both the Foundation and Practitioner courses through our self-paced e-learning, you will develop an understanding of the methodology and learn how to effectively adapt it to any project.
The PRINCE2® 7 Foundation and Practitioner Masterclass is PeopleCert Accredited and guarantees to take you from PRINCE2 Novice to PRINCE2 Practitioner with our famous video learning, study guides and practice exams.
What Does the Masterclass Cover?
The PRINCE2 Foundation examination assesses your knowledge and comprehension of the PRINCE2 project management methodology as detailed in the syllabus. The PRINCE2 Practitioner examination, on the other hand, gauges your ability to apply and tailor the PRINCE2 method. Candidates who pass the Practitioner exam should be able to start implementing the method on an actual project with some guidance. However, their effectiveness may differ based on their experience in project management, the complexity of the project, and the level of support they receive in their work environment.